Australia’s Ichthys LNG to restart liquefaction train

  • : Natural gas
  • 24/07/26

The second liquefaction train at Australia's 9.3mn t/yr Ichthys LNG export terminal plans to resume partial operations today, after going off line unexpectedly during 18-19 July, according to traders.

The export facility is operated by Japanese upstream firm Inpex.

Repairs at the affected train could take up to a month before it returns to full production, although the train is expected to restart by this weekend, according to market participants. Attempts to restart train two could take place by 26 July. Some delays to deliveries from the facility are expected, although there are also unconfirmed reports that up to two cargoes may have already been cancelled at the time of writing.

The overall impact on the market is likely to be limited for now, with continuing weak spot demand from northeast Asian importers. Some term buyers previously requested for their deliveries to be deferred, traders said, although it is unclear just how many requests for deferment were received.

But other participants have pointed out that the winter restocking season could soon start and any further impediments to train two's restart could lift prices. Recent temperatures in Japan have been higher than expected, with at least a 70pc probability of above-normal temperatures over the vast majority of the country until 23 August, according to the latest forecast issued by the Japan Meteorological Agency on 25 July.

At least one Japanese utility may be considering spot purchases for August, owing to higher-than-expected power consumption because of warmer temperatures. But at least two other Japanese firms could be looking to sell a September and an October cargo each, traders said, which could indicate that the spot market is still sufficiently well-supplied to cope with additional demand from Japanese utilities.

The 174,000m³ Grace Freesia departed from Ichthys on 25 July after loading an LNG cargo, according to ship tracking data from Kpler. The export terminal sold a spot cargo for loading over 2-6 June at around high-$9s/mn Btu through a tender that closed on 10 May, but further details are unclear.

The US' 17.3mn t/yr Freeport export terminal also faced issues restarting since it was first taken off line on 7 July as a precautionary measure against Hurricane Beryl. The terminal loaded its first cargo on 21 July. All three trains are likely to be back on line as of 26 July, although production at the facility should still be closely monitored, traders said.


Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more