The main chamber of the Wilson Lock in Alabama along the Tennessee River is tentatively scheduled to reopen in four months, according to the US Army Corps of Engineers (Corps).
The Corps expects to finish phase two of dewatering repairs on the lock on 20 April, after which navigation can resume through the main chamber of the lock.
The timeline for reopening may shift depending on final assessments, the Corps said.
Delays at the lock average around 12 days through the auxiliary chamber, according to the Lock Status Report by the Corps. Delays at the lock should wane during year-end holidays but pick up as spring approaches, barge carriers said.
The main chamber of the Wilson Lock will have been closed for nearly seven months by the April reopening after closing on 25 September.