Adds comment.

Mexico expanded its clean energy certificates (CELs) to legacy, mostly hydropower generators previously excluded from the program, which was created primarily to boost new wind and solar power.

The expansion will apply to low-carbon generators built before 2014, which in Mexico will mostly be applicable to hydropower plants, most of which are non-operational, and a small amount of nuclear and geothermal generation, based on the final energy ministry (Sener) decision published in the federal record yesterday.

Until this change, only clean energy power projects built after the 2014 energy reform qualified for CELs.

Expanding Mexico's clean energy certificates (CELs) to apply to older hydroelectric plants under a new energy ministry proposal would dilute the program's goal of promoting new renewable power generation, industry participants complained.

The change could disrupt the incipient market for wind and solar, participants have said as their combined capacity only accounts for 9.4pc. Hydro and nuclear account for 18pc and 2.3pc of Mexico's total installed capacity, respectively, already. CFE's clean energy capacity could flood the CELs market and industry observers say that would place CFE's CELs at an advantage ahead of those of smaller, private wind and power producers.

Mexican business council CCE said the move would risk up to $9bn already lined up for wind and solar projects, which were relying on CELs to develop several farms. Some 60 recommendations were filed to oversight body Conamer before Sener's proposal was enacted yesterday, but none were specifically addressed under the new arrangement.

"The decision undermines the only mechanism contemplated by law ... to meet the national 35pc clean energy obligatory targets," the CCE said. "We will recur to legal means to guarantee that the adherence to the norms continues to be a stimulus for investments, sustainability and the prosperity of Mexico."

Before President Andres Manuel Lopez Obrador took office, the former administration aimed to increase clean energy capacity by holding three long-term power auctions for 15- to 20-year supply contracts, clean energy certificates and stand-by capacity. A fourth auction was cancelled in January, a month after Lopez Obrador took office.

CFE dominates power generation in Mexico despite the 2014 energy reform. CFE produces 54pc of total power in Mexico from all feedstocks.

Targets according to Mexico's energy transition law mandate for the country's "clean energy" sources to generate 30pc of the total by 2021 and 35pc by 2024. To meet those targets, conventional power generators — including CFE and industrial companies — are required to present CELs for 5.8pc of total generation in 2019 and up to 35pc by 2024.

Of Mexico's 86 hydro power plants, CFE has 59 hydro power plants nationwide but only 14 are active with a combined capacity of 10,583MW. The largest capacity lies in Chiapas and Guerrero states and CFE controls the largest capacity — the rest are small, mostly inactive hydro producers. Generadora Fenix operates the only major, active private hydro plant, the 109MW Necaxa.

Under Lopez Obrador's hydro revamp plan, Sener plans to add 15MW as early as December 2020, then 60MW from six revamped turbines in April 2021, 116MW in April 2022 from 15 units, 204MW from 19 units in April 2023, 82MW from 10 units in 2024 and 12MW from one plant in 2025.

The priority project is the Chiapas' 240MW Chicoasen II hydropower plant, which according to CFE director Manuel Bartlett will be brought online as early as 2020. The plant was expected to come online in September 2018 but was delayed because of legal issues.

The new plant is part of CFE's and Mexico's largest hydro plant, the 2,400MW Chicoasen complex. Mexico projected a budget Ps10.2bn ($540mn) for the project in 2019 and Ps100mn will be allocated for the plant's development in 2020.

As a result, Sener expects Mexico's hydro capacity to jump at least to 13,099MW thanks to revamps — plus the new 240MW at Chicoasen II — by 2024 from 12,609MW today.

By end-2018, wind power and solar installed capacity reached 6.8pc and 2.6pc, respectively. Mexico's national wind association AMDEE expects wind capacity to increase to 12,000MW by end-2022 from some 5,000MW today.

But natural-gas fired, combined-cycle plants make up 37pc of total domestic capacity and they are the backbone of Mexican power generation: they generate 51pc of the country's annual needs. Thermal plants follow with 13pc.

Total power generation from all clean sources combined reached 19pc of Mexico's total by end-2018. Of these, hydro accounts for 10pc, nuclear for 4.3pc, wind for 3.9pc and solar for a marginal 0.7pc. CFE generates over 50pc of Mexico's clean energy.


Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

16/05/25

Trump says US will soon set new tariff rates

Trump says US will soon set new tariff rates

Washington, 16 May (Argus) — The US will unilaterally set new tariff rates on imports from select trading partners instead of holding negotiations over import tax levels, President Donald Trump said today. In the next 2-3 weeks "we'll be telling people what they will be paying to do business in the US," Trump told a group of US and UAE business executives in Abu Dhabi today. Trump contended that more than 150 US trading partners have expressed interest in negotiating with his administration, adding that "you're not able to see that many countries." Trump's administration since 5 April imposed a 10pc baseline tariff on imports from nearly every US trading partner — with the notable exception of Canada, Mexico and Russia. Trump paused his so-called "reciprocal tariffs" until 8 July, nominally to give his administration time to negotiate with foreign countries subject to those punitive rates. The reciprocal tariffs would have added another 10pc on top of his baseline tariff for imports from the EU, while the cumulative rate would have been as high as 69pc on imports from Vietnam. Trump in April suggested that 200 deals with foreign trade partners were in the works. Treasury secretary Scott Bessent has said the US is only negotiating with the top 18 trading partners. The trade "deals" clinched by the Trump administration so far merely set out terms of negotiations for agreements to be negotiated at a later date. The US-UK preliminary deal would keep the US tariff rate on imports from the UK at 10pc, while providing a quota for UK-manufactured cars and, possibly, for steel and aluminum. The US-UK document, concluded on 9 May, explicitly states that it "does not constitute a legally binding agreement." The US-China understanding, reached on 12 May, went further by rolling back some of the punitive tariff rates but left larger trade issues to be resolved at a later date. The Trump administration would keep in place a 20pc extra tariff imposed on imports from China in February-March and a 10pc baseline reciprocal tariff imposed in April. The US will pause its additional 24pc reciprocal tariff on imports from China until 10 August. Conversely, China will keep in place tariffs of 10-15pc on US energy commodity imports that it imposed on 4 February, and 10-15pc tariffs on US agricultural imports, imposed in March. It will maintain a 10pc tariff on all imports from the US that was imposed in April, but will pause an additional 24pc tariff on all US imports until 10 August. These rates are on top of baseline import tariffs that the US and China were charging before January 2025. By Haik Gugarats Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

Kuwait's Kufpec gets OK to develop Indonesian gas field


16/05/25
16/05/25

Kuwait's Kufpec gets OK to develop Indonesian gas field

Singapore, 16 May (Argus) — Kuwait's Kufpec, a unit of state-owned KPC, has won approval from the Indonesian government for a plan of development for the Anambas gas field located in the West Natuna Sea offshore Indonesia. The Anambas field is located in the Natuna basin and has an estimated gas output of about 55mn ft³/d. Kufpec will invest around $1.54bn into the development of the field, which is planned to come on stream in 2028. The approved plan of development outlines a phased strategy to unlock the gas and condensate potential of the field, said upstream regulator SKK Migas. The regulator will encourage Kufpec to accelerate efforts and bring the project on stream by the fourth quarter of 2027, said the head of SKK Migas, Djoko Siswanto. The development of the field will include drilling production wells and installing subsea pipelines to transport gas from Anambas to existing facilities in the West Natuna transportation system. Kufpec in 2022 announced the discovery of gas and condensate at the Anambas-2X well in the Anambas block. The Anambas block was awarded to Kufpec Indonesia in 2019 through a bidding process. The company holds a 100pc participating interest in the block and has a 30-year production sharing licence, including a six-year exploration period. The approval of the plan of development marks a step towards the project's final investment decision. It also shows that the upstream oil and gas sector in Indonesia is still attractive to domestic and foreign firms, said Djoko. The field is expected to be able to transport gas to domestic and regional markets, support Indonesia's energy security, and drive economic growth, according to SKK Migas. Indonesia continues to prioritise oil and gas expansion to maintain economic growth. Investment in oil and gas rose from $14.9bn in 2023 to $17.5bn in 2024, according to the country's energy ministry. By Prethika Nair Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

Austrian PV additions fall 100MW on year in 1Q


15/05/25
15/05/25

Austrian PV additions fall 100MW on year in 1Q

London, 15 May (Argus) — Austrian solar photovoltaic (PV) capacity additions fell by around 100MW on the year in the first quarter of 2025, solar association PV Austria told Argus , a decrease of around 20pc. Newly installed PV capacity in January-March stood at 399MW, PV Austria said, compared with 497MW added in the first quarter of last year, according to data from grid regulator E-control. But late reports from Austria's distribution system operators may still cause a slight uptick in capacity addition numbers for the last quarter, PV Austria said. The association largely attributed the fall in solar additions to uncertainty around government policies, which "compromised" planning security and "jeopardised" investments into renewable energy, it told Argus . And it cited the "abrupt" end of the VAT exemption for small PV systems as well as the extension and tightening of the energy crisis contribution as further reasons for the decline. PV Austria called on the government to pass the electricity industry act (ElWG) and the renewable energy expansion acceleration act (EABG) as soon as possible. The government in February pledged to pass the ElWG in the summer of this year. Austria had just under 8.3GW of solar capacity installed as of the start of January, the latest data from transmission system operator APG show. Solar output more than doubled on the year in 2024 and APG has several times highlighted the challenges posed by increased PV capacity for demand forecasting and grid stability during times of solar peaks, when excess power must either be transported abroad or to storage power plants and can also lead to curtailments at wind and hydropower units. By John Horstmann Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

UK establishes public energy company


15/05/25
15/05/25

UK establishes public energy company

London, 15 May (Argus) — The UK parliament has passed a bill establishing a publicly owned energy company, Great British Energy (GBE), to support the nation's renewable energy ambitions. The company, funded with £8.3bn ($11.02bn) over the current parliamentary term, aims to accelerate renewable energy projects, enhance energy security, and support job creation, the department for energy security and net zero (Desnz) announced on Thursday. GBE will invest in clean energy initiatives, including technologies such as floating offshore wind, and collaborate with private companies to expand renewable energy capacity. The government states the company will help stabilise energy costs by reducing reliance on fossil fuels. The bill includes £200mn for renewable energy projects, such as rooftop solar for schools, hospitals, and communities. It has also committed £300mn to develop the UK's offshore wind supply chain, supporting manufacturing of components such as cables and platforms. The legislation received approval from the devolved governments of Scotland, Wales, and Northern Ireland, enabling GBE to operate across the UK. Desnz secretary of state Ed Miliband is expected to outline GBE's strategic priorities "soon", specifying technology focus areas and investment criteria. The government sees GBE as a key part of its plan to transition to clean energy and stimulate economic growth through a "modern industrial strategy", it said. Industry body Energy UK welcomed the bill's passage. "[GBE] can play a vital role in making the government's clean energy ambitions a reality by attracting extra private sector investment," chief executive Dhara Vyas said. By Timothy Santonastaso Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

Greece’s Alexandroupolis LNG off line until mid-Aug


15/05/25
15/05/25

Greece’s Alexandroupolis LNG off line until mid-Aug

London, 15 May (Argus) — Greece's 4.3mn t/yr Alexandroupolis LNG import terminal will remain off line until 15 August, after which it will return to 25pc of capacity for the remainder of the gas year, an updated urgent market message (UMM) from operator Gastrade says. The terminal has been off line since 28 January because of damage to the booster pumps on the floating storage and regasification unit, Gastrade said, and it will remain fully unavailable until 15 August, after which onward regasification services will resume capped at 25pc of maximum capacity, or about 42 GWh/d, with available redundancy for the booster pumps. This availability will be offered for 15 August-30 September only under "certain operational and commercial conditions", Gastrade specified, and several market participants were unsure of what this phrase meant or whether regasification would in fact be possible at all during this period. From the start of the new gas year on 1 October, the 25pc cap will be lifted, but "certain operation constraints may remain for a limited period of time", the operator said. The previous version of the the UMM listed the shutdown end date as 15 May, although Gastrade had already told Argus in April that it did not expect to return to full operations until October . By Brendan A'Hearn Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.