Construction resumes at Indonesian coal power plant

  • : Coal, Electricity
  • 21/02/15

Construction of a new 400MW coal-fired power plant in Indonesia's Aceh regency has resumed after being halted early last year because of the Covid-19 pandemic.

The $600mn project is being developed by a consortium composed of China Datang Overseas Investment, Indonesian state-owned construction firm Pembangunan Perumahan's subsidiary PP Energy and power services company Sumberdaya Sewatama. It is scheduled to be completed in late 2023 and begin commercial operations in 2024. The power plant is expected to consume at least 1.2mn t/yr of coal, 90pc of which will be sourced from Kalimantan on Indonesian Borneo.

Construction was halted in March last year because of the pandemic, with PP Energy submitting a force majeure notification to state-owned transmission and generation firm PLN. The project was originally scheduled for completion in 2021 but has been delayed by land issues and other legal constraints.

Construction work is expected to accelerate over the next two years as Indonesia starts to recover from the Covid-19 pandemic, PP Energy said. The plant will operate as a base-load facility and help to alleviate electricity shortages in the Aceh Jaya, west Aceh, southwest Aceh and Nagan Raya areas.

The project is part of the Indonesian government's 35GW power generation programme. It will operate as an independent power producer with a 25-year supply contract starting from its commercial operation date under a power purchase agreement between PLN and the consortium partners.

By Antonio delos Reyes


Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

24/12/26

Viewpoint: US gas market poised for more volatility

Viewpoint: US gas market poised for more volatility

New York, 26 December (Argus) — US natural gas markets may be subjected to more dramatic price swings in 2025 as growing LNG exports and increasingly price-sensitive producers place greater pressure on the US' stagnant gas storage capacity. Those price swings could pose challenges for consumers without ample access to gas supplies, as well as producers interested in keeping some output unhedged to capture potentially higher prices without taking on excessive financial risk. But volatility may also present opportunities for traders looking to exploit unstable price spreads, and for producers that can adapt their operations to fit a more unpredictable pricing environment. Calm before the storm High storage levels and low spot prices this year — averaging $2.11/mmBtu through November this year at the US benchmark Henry Hub — triggered by an unusually warm 2023-24 winter, may have obscured some of the structural factors pushing the US gas market into a more volatile future. But those structural factors remain and loom increasingly large for prices. The US has moved from a roughly 60 Bcf/d (1.7bn m³/d) market eight years ago to a more than 100 Bcf/d market today, "and we haven't grown our storage capacity at all", Rich Brockmeyer, head of North American gas and power at commodity trading house Gunvor, said earlier this year. As supply and demand for US gas grow, the country's roughly 4.7-Tcf storage capacity becomes ever less effective in stemming demand shocks, such as extreme winter weather events, which can more rapidly draw down inventories than in years past. Additionally, a growing share of US gas is being consumed by LNG export terminals being built and expanded on the US Gulf coast. When those facilities encounter unexpected problems and cease operations — as has happened numerous times at the 2 Bcf/d Freeport LNG terminal in Texas in recent years — volumes that were previously being liquefied and sent overseas were instead backed up into the domestic market, crushing prices. More LNG exports may mean more opportunities for such supply shocks. US LNG exports are expected to increase by 15pc to almost 14 Bcf/d in 2025 as operations begin at Venture Global's planned 27.2mn t/yr Plaquemines facility in Louisiana and Cheniere's 11.5mn t/yr Corpus Christi, Texas, stage 3 expansion, US Energy Information Administration data show. Spot price volatility will be most acutely felt in regions like New England that lack underground gas storage. "In areas like the Gulf coast, where you have a lot of storage, it won't be a problem," Alan Armstrong, chief executive of Williams, the largest US gas pipeline company, told Argus in an interview. Producers' trade-off Volatile gas markets are a mixed bag for producers, many of whom profit from volatility while also struggling to plan and budget based on uncertain revenues for unhedged volumes. Though insufficient gas storage deprives the market of stability, "from the standpoint of a marketing and trading guy that's trying to manage my gas supply to customers and my trading book, I love volatility",said Dennis Price, vice president of marketing and trading at Expand Energy, the largest US gas producer by volume. BP chief financial officer Sinead Gorman in November 2023 specifically named Freeport LNG's eight-month-long shutdown in 2022-23 from a fire as a driver of volatility in the global gas market. The supermajor was able to exploit the "incredibly fragile" gas market, she said, which was a key factor driving the success of its integrated gas business. "Those opportunities are what we typically seek and enjoy," Gorman said. Increasingly, producers have also been adapting to a more volatile market by switching production on and off in response to prices, but often without revealing the price at which a supply response will occur. Expand Energy, for instance, told investors in October that it was amassing drilled but uncompleted wells and wells that had yet to be brought on line, which it could activate relatively quickly when prices rise. It declined to name the price at which that would occur. Market participants, attempting to price in this phenomenon by anticipating producers' next moves may respond more dramatically to supply signals than in the past, when production was steadier. Producers' increased responsiveness to prices could help to balance the market somewhat, though more aggressive intervention into operations could take a toll on well performance and pipelines, FactSet senior energy analyst Connor McLean said. Producers are "treating the reservoir itself like a storage facility", Price said. By Julian Hast Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Japan’s Chugoku restarts Shimane nuclear reactor early


24/12/23
24/12/23

Japan’s Chugoku restarts Shimane nuclear reactor early

Osaka, 23 December (Argus) — Japanese utility Chugoku Electric Power restarted the 820MW Shimane No.2 nuclear reactor for test operations on 23 December, two days earlier than originally planned. The No.2 reactor at Shimane in west Japan's Shimane prefecture was reconnected to the country's power grids for the first time in nearly 13 years, after the reactor shut down in January 2012 for stricter safety inspections following the 2011 Fukushima nuclear meltdown disaster. Chugoku reactivated the Shimane No.2 reactor on 7 December, aiming to resume power generation on 25 December. But the target date for commercial operations remained unchanged on 10 January, despite the earlier than expected restart. The Shimane No.2 reactor will be a vital power source as the sole nuclear fleet in the Chugoku area, to help enhance the resilience of the power supply structure, stabilise retail electricity prices and reduce CO2 emissions, said Japan Atomic Industrial Forum's president Hideki Masui on 23 December. The Shimane No.2 reactor is the second boiling water reactor (BWR) to be restarted after the Fukushima disaster, following the 825MW Onagawa No.2 BWR unit that resumed test generation on 15 November, with normal operations scheduled to restart on 26 December. The BWR is the same type as that involved in the meltdown at the Fukushima Daiichi plant. The restart of the two BWRs would pave the way for Japan's nuclear restoration, as 15 BWRs — including advanced BWRs — are still closed in the wake of the Fukushima disaster. Japan has restored 14 reactors as of 23 December, including the Shimane and Onagaw reactors, of which 12 are installed with a pressurised water reactor (PWR) design. Nuclear power's share The Japanese government last week set a target of 20pc for nuclear power's share in the country's draft power mix for the April 2040-March 2041 fiscal year, under the triennial review for the country's Strategic Energy Plan (SEP). Tokyo is seeking to restart all existing reactors to achieve the 20pc goal, adding that replacement reactors would also be possible. The draft SEP allows nuclear power operators that had decommissioned reactors to build next-generation reactors at their nuclear sites, not limited to the same site. The previous SEP did not mention building new reactors or replacements. Japan's Federation of Electric Power Companies (FEPC) has applauded this progress, but FEPC chairman Kingo Hayashi noted that it was disappointing the SEP did not mention a nuclear capacity target which the FEPC had requested. It also did not include building new reactors or the expansion of existing nuclear plants, Hayashi added. By Motoko Hasegawa Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Brazil Bndes invests more in Sao Paulo EV fleet


24/12/20
24/12/20

Brazil Bndes invests more in Sao Paulo EV fleet

Sao Paulo, 20 December (Argus) — Brazil's Bndes development bank approved R94.8mn ($15.6mn) in financing for transport company MobiBrasil to buy 87 electric buses in Sao Paulo city. The environment ministry's climate fund — created to finance climate change mitigation projects and Bndes — will be responsible for R45mn. A federal fund to provide financial security to the unemployed, dubbed FGTS, will be responsible for the remaining R49.8mn. This is Bndes' first operation using FGTS resources. Earlier this month, Bndes said it will invest R2.5bn to buy 1,300 EV-buses in Sao Paulo city . On 9 December, the city's council postponed the bus fleet transition from diesel-powered to EVs to 2054 from the previous 2038 deadline. By Maria Frazatto Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

US government agencies set to shut down


24/12/20
24/12/20

US government agencies set to shut down

Washington, 20 December (Argus) — US federal agencies would have to furlough millions of workers and curtail permitting and regulatory services if no agreement is reached by Friday at 11:59pm ET to extend funding for the government. US president-elect Donald Trump and his allies — including Tesla chief executive Elon Musk — on 18 December upended a spending deal US House of Representatives speaker Mike Johnson (R-Louisiana) had negotiated with Democratic lawmakers in the House and the Senate. Trump endorsed an alternative proposal that Johnson put together, but that measure failed in a 174-235 vote late on Thursday, with 38 Republicans and nearly every Democrat voting against it. Trump via social media today indicated he would not push for a new funding bill. "If there is going to be a shutdown of government, let it begin now, under the Biden Administration, not after January 20th, under 'TRUMP,'" he wrote. There was little to indicate as of Friday morning that Trump, Republican congressional leadership and lawmakers were negotiating in earnest to avert a shutdown. The House Republican conference is due to meet in the afternoon to weigh its next steps. President Joe Biden said he would support the first funding deal that Johnson negotiated with the Democratic lawmakers. "Republicans are doing the bidding of their billionaire benefactors at the expense of hardworking Americans," the White House said. Any agreement on funding the government will have to secure the approval of the House Republican leadership and all factions of the Republican majority in the House, who appear to be looking for cues from Trump and Musk on how to proceed. Any deal would then require the support of at least 60 House Democrats to clear the procedural barriers, before it reaches the Senate where the Democrats hold a majority. The same factors will be in play even if the shutdown extends into early 2025. The Republicans are set to take the majority in the Senate when new Congress meets on 3 January. But their House majority will be even slimmer, at 219-215, requiring cooperation of Democratic lawmakers and the Biden administration. What happens when the government shuts down? Some agencies are able to continue operations in the event of a funding lapse. Air travel is unlikely to face immediate interruptions because key federal workers are considered "essential," but some work on permits, agricultural and import data, and regulations could be curtailed. The US Federal Energy Regulatory Commission has funding to get through a "short-term" shutdown but could be affected by a longer shutdown, chairman Willie Phillips said. The US Department of Energy, which includes the Energy Information Administration and its critical energy data provision services, expects "no disruptions" if funding lapses for 1-5 days, according to its shutdown plan. The US Environmental Protection Agency would furlough about 90pc of its nearly 17,000 staff in the event of a shutdown, according to a plan it updated earlier this year. The Interior Department's shutdown contingency plan calls for the Bureau of Land Management (BLM) to furlough 4,900 out of its nearly 10,000 employees. BLM, which is responsible for permitting oil, gas and coal activities on the US federal land, would cease nearly all functions other than law enforcement and emergency response. Interior's Bureau of Safety and Environmental Enforcement, which oversees offshore leases, would continue permitting activities but would furlough 60pc of its staff after its funding lapses. The US Bureau of Ocean Energy Management will keep processing some oil and gas exploration plans with an on-call group of 40 exempted personnel, such as time-sensitive actions related to ongoing work. The shutdown also affects multiple other regulatory and permitting functions across other government agencies, including the Departments of Agriculture, Transportation and Treasury. By Haik Gugarats Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Australia’s Cleanaway, LMS to produce landfill gas


24/12/20
24/12/20

Australia’s Cleanaway, LMS to produce landfill gas

Sydney, 20 December (Argus) — Australian waste management operator Cleanaway and bioenergy firm LMS Energy will partner on a 22MW landfill gas-fired power station at Cleanaway's Lucas Heights facility near the city of Sydney. Cleanaway, Australia's largest publicly listed waste management firm, will receive exclusive rights to landfill gas produced at Lucas Heights for 20 years, the company said on 20 December. LMS will invest A$46mn ($29mn) in new bioelectricity assets, including a 22MW generator. Tightening gas markets owing to underinvestment in new supply has led to speculation that more waste-to-energy plants could be brought on line in coming years, especially in the southern regions. Landfill gas projects receive Australian Carbon Credit Units (ACCUs) by avoiding methane releases, with the total ACCU quantity calculated after a default baseline of 30pc is deducted for projects beginning after 2015. A total of 42.6mn ACCUs were issued to landfill gas projects since the start of the ACCU scheme in 2011, 27pc of the total 155.7mn and the second-largest volume after human-induced regeneration (HIR) methods at 46.68mn. Canberra is reviewing ACCU issuance for these projects, and wants most projects to directly measure methane levels in captured landfill gas to avoid overestimation. Landfill gas operations which generate electricity from the captured gases can also receive large-scale generation certificates (LGCs). LMS has 70 projects currently registered at the Clean Energy Regulator (CER) and has received 24.57mn ACCUs since the start of the scheme. This is the largest volume for any single project proponent, just ahead of Australian environmental market investor GreenCollar's subsidiary Terra Carbon with 23.57mn units. Cleanaway received almost 1mn ACCUs from two projects and has four other projects that have yet to earn ACCUs. By Tom Major and Juan Weik Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Generic Hero Banner

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more