Latest market news

US data center growth effect on coal may be limited

  • : Coal, Electricity
  • 24/10/24

The US coal industry is pondering ways to respond to the projected boost in domestic power demand linked to planned data centers in the pipeline, but the centers' effect on coal could be mixed or limited.

A number of projects have been announced for coming years. But generators are still grappling with uncertain estimates of which major projects in the US will come to fruition, where they will be located and other criteria that will drive demand.

"Data center companies are shopping around in different utilities' territories and showing up multiple times and being double counted", said Laurie Williams, director of the Sierra Club's Beyond Coal Campaign.

According to the National Telecommunications and Information Administration, there are more than 5,000 data centers currently in the US, and demand for data centers in the country is projected to grow by 9pc annually through 2030. Approximately 8-10 larger data centers could be developed across the US in coming years. A number of large-scale projects, which could include so-called 'big tech' — Apple, Alphabet (Google), Amazon, Facebook (Meta), and Microsoft — are going through the feasibility study phase, Argus sources said.

The Sierra Club is expecting electricity demand from data centers to increase anywhere between 5pc-20pc/yr. Some generators that spoke with Argus said they project growth of 9pc/yr, while an "organic" increase in electricity demand was previously expected to be 2pc-3pc.

The US Energy Information Administration (EIA) earlier this month projected commercial electricity sales would rise by 3pc this year and 1pc in 2025, helping to boost overall electricity generation.

"It is fair to say that the growth of commercial demand for electricity is at least due in part to the effect of data center development," said US Energy Information Administration (EIA) economist Jonathan Church. "We cannot, however, provide a precise estimate of what that effect is or what data center growth is."

So far this year, US coal-fired generation has fallen as lower-cost natural gas, nuclear and renewable generation maintained or expanded their leads over coal in the generation mix. EIA expects coal-fired generation to fall in 2024 and edge higher in 2025.

A number of factors still need to come together before more certain projections of data centers' impact on the US coal industry are released, market participants said. Those include state environmental goals and federal regulations, availability of overall energy infrastructure and different generation types, and the approach that the IT sector will pursue when planning new projects.

At least some IT companies are favoring lower-CO2 emitting generation. For example, Microsoft, Amazon and Alphabet recently have signed agreements to use nuclear or renewable generation for some projects. Other developers have indicated wanting to buy generation from wholesale electricity markets.

In addition, US utilities continue to retire coal units to comply with US Environmental Protection Agency (EPA) rules. The amount of coal-fired generating capacity available in the US is expected to shrink to 163.7GW by the end of 2025 from 177GW in 2023, according to EIA.

Longer life for coal plants?

But some in the electric power industry are concerned about enough generating capacity being available to meet expected load growth because, in some cases, new generating facilities need to be built to provide the amount of power needed.

"With the level of demand increasing, all energy resource consumption will increase," Utah Office of Energy Development acting director Dusty Monks said. "It is not out of the realm of possibility to say these industries (data centers and AI) will surpass the energy use of traditional customers in the next 10-15 years".

Some generators that project increased electricity demand driven by data centers have proposed extending the operation of their coal plants. Limited natural gas pipeline infrastructure in some regions and mine-mouth power plants also support increased coal consumption to some extent.

Alliant Energy delayed the coal-to-gas conversion of a Wisconsin plant by three years to 2028. Duke Energy may put off some coal-fired power plant unit retirements in Indiana, with the intention of burning coal in the state until 2038.

Elsewhere in the US, companies representing up to 15GW of load — mostly data centers — are seeking service from American Electric Power by 2030.

Other utilities are continuing to convert coal-fired facilities to natural gas instead of retiring them. While the EPA has rolled out rules for gas plant emissions, gas units may still be more competitive financially and technologically over coal since gas prices have been lower and new gas units generally are more efficient when used as a backup to intermittent renewable energy. Even power plants in Utah, which traditionally favored coal, generated nearly the same amount of power from gas and coal over the first seven months of 2024 (see chart).

US coal producers are paying close attention to plans for data centers and possible effects on coal demand but are still scaling back output. US coal mines' output totaled 591.5mn st (536.6mn metric tonnes) this year through 12 October, down by nearly 13pc from the same period in 2023, according to EIA data.

Some of the states with the greatest growth in commercial electricity demand still have relatively large amounts of coal-fired generation, the EIA data show. But many of these states are also natural gas generation hubs.

This includes Virginia and Texas, which had an outsized share of commercial generation growth last year.

The fate and plans of data center projects in the pipeline as well as economics, regulation and company preference will determine the outcome for coal generation.

Generation in selected states, January-July 2023-24MWh
Coal-fired generationGas-fired generationRenewablesTotal
States20242023202420232024202320242023
Arizona5,593,2836,228,90728,916,43327,939,45810,905,9039,452,57064,588,78462,083,941
% of total8.7%10%44.8%45.0%16.9%15.2%
Georgia10,887,2418,828,63834,824,57735,144,5867,318,8826,552,34283,496,20273,139,216
% of total13%12.1%42%48.1%8.8%9.0%
North Dakota13,382,05912,873,0171,242,1381,267,1759,657,0149,606,92724,336,70123,816,246
% of total55%54.1%5.1%5.3%39.7%40.3%
Ohio17,756,48916,619,60748,526,51344,227,6234,370,9822,709,43481,756,36273,249,449
% of total22%22.7%59%60.4%5.3%3.7%
Oklahoma3,142,1292,855,13927,714,09325,662,25825,081,02823,054,48156,121,79051,712,526
% of total5.6%5.5%49%49.6%44.7%44.6%
South Carolina9,885,9018,792,04912,670,28613,811,0183,254,3623,198,20559,528,87858,292,079
% of total16.6%15.1%21.3%23.7%5.5%5.5%
Texas34,791,19439,405,356160,458,170154,904,39399,240,55690,277,178319,162,821310,039,675
% of total10.9%12.7%50%50.0%31.1%29.1%
Utah6,954,2338,802,6716,720,4816,762,0463,452,9743,331,94018,090,48019,499,948
% of total38.4%45.1%37%34.7%19.1%17.1%
Virginia1,190,771990,25735,852,01528,696,5474,885,2614,143,97059,761,59052,708,332
% of total2.0%1.9%60%54.4%8.2%7.9%
Wyoming13,486,43716,573,7412,756,7751,141,7966,258,3595,759,27222,786,92823,743,769
% of total59.2%69.8%12%5%27.5%24.3%

Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

24/12/23

Japan’s Chugoku restarts Shimane nuclear reactor early

Japan’s Chugoku restarts Shimane nuclear reactor early

Osaka, 23 December (Argus) — Japanese utility Chugoku Electric Power restarted the 820MW Shimane No.2 nuclear reactor for test operations on 23 December, two days earlier than originally planned. The No.2 reactor at Shimane in west Japan's Shimane prefecture was reconnected to the country's power grids for the first time in nearly 13 years, after the reactor shut down in January 2012 for stricter safety inspections following the 2011 Fukushima nuclear meltdown disaster. Chugoku reactivated the Shimane No.2 reactor on 7 December, aiming to resume power generation on 25 December. But the target date for commercial operations remained unchanged on 10 January, despite the earlier than expected restart. The Shimane No.2 reactor will be a vital power source as the sole nuclear fleet in the Chugoku area, to help enhance the resilience of the power supply structure, stabilise retail electricity prices and reduce CO2 emissions, said Japan Atomic Industrial Forum's president Hideki Masui on 23 December. The Shimane No.2 reactor is the second boiling water reactor (BWR) to be restarted after the Fukushima disaster, following the 825MW Onagawa No.2 BWR unit that resumed test generation on 15 November, with normal operations scheduled to restart on 26 December. The BWR is the same type as that involved in the meltdown at the Fukushima Daiichi plant. The restart of the two BWRs would pave the way for Japan's nuclear restoration, as 15 BWRs — including advanced BWRs — are still closed in the wake of the Fukushima disaster. Japan has restored 14 reactors as of 23 December, including the Shimane and Onagaw reactors, of which 12 are installed with a pressurised water reactor (PWR) design. Nuclear power's share The Japanese government last week set a target of 20pc for nuclear power's share in the country's draft power mix for the April 2040-March 2041 fiscal year, under the triennial review for the country's Strategic Energy Plan (SEP). Tokyo is seeking to restart all existing reactors to achieve the 20pc goal, adding that replacement reactors would also be possible. The draft SEP allows nuclear power operators that had decommissioned reactors to build next-generation reactors at their nuclear sites, not limited to the same site. The previous SEP did not mention building new reactors or replacements. Japan's Federation of Electric Power Companies (FEPC) has applauded this progress, but FEPC chairman Kingo Hayashi noted that it was disappointing the SEP did not mention a nuclear capacity target which the FEPC had requested. It also did not include building new reactors or the expansion of existing nuclear plants, Hayashi added. By Motoko Hasegawa Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Brazil Bndes invests more in Sao Paulo EV fleet


24/12/20
24/12/20

Brazil Bndes invests more in Sao Paulo EV fleet

Sao Paulo, 20 December (Argus) — Brazil's Bndes development bank approved R94.8mn ($15.6mn) in financing for transport company MobiBrasil to buy 87 electric buses in Sao Paulo city. The environment ministry's climate fund — created to finance climate change mitigation projects and Bndes — will be responsible for R45mn. A federal fund to provide financial security to the unemployed, dubbed FGTS, will be responsible for the remaining R49.8mn. This is Bndes' first operation using FGTS resources. Earlier this month, Bndes said it will invest R2.5bn to buy 1,300 EV-buses in Sao Paulo city . On 9 December, the city's council postponed the bus fleet transition from diesel-powered to EVs to 2054 from the previous 2038 deadline. By Maria Frazatto Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

US government agencies set to shut down


24/12/20
24/12/20

US government agencies set to shut down

Washington, 20 December (Argus) — US federal agencies would have to furlough millions of workers and curtail permitting and regulatory services if no agreement is reached by Friday at 11:59pm ET to extend funding for the government. US president-elect Donald Trump and his allies — including Tesla chief executive Elon Musk — on 18 December upended a spending deal US House of Representatives speaker Mike Johnson (R-Louisiana) had negotiated with Democratic lawmakers in the House and the Senate. Trump endorsed an alternative proposal that Johnson put together, but that measure failed in a 174-235 vote late on Thursday, with 38 Republicans and nearly every Democrat voting against it. Trump via social media today indicated he would not push for a new funding bill. "If there is going to be a shutdown of government, let it begin now, under the Biden Administration, not after January 20th, under 'TRUMP,'" he wrote. There was little to indicate as of Friday morning that Trump, Republican congressional leadership and lawmakers were negotiating in earnest to avert a shutdown. The House Republican conference is due to meet in the afternoon to weigh its next steps. President Joe Biden said he would support the first funding deal that Johnson negotiated with the Democratic lawmakers. "Republicans are doing the bidding of their billionaire benefactors at the expense of hardworking Americans," the White House said. Any agreement on funding the government will have to secure the approval of the House Republican leadership and all factions of the Republican majority in the House, who appear to be looking for cues from Trump and Musk on how to proceed. Any deal would then require the support of at least 60 House Democrats to clear the procedural barriers, before it reaches the Senate where the Democrats hold a majority. The same factors will be in play even if the shutdown extends into early 2025. The Republicans are set to take the majority in the Senate when new Congress meets on 3 January. But their House majority will be even slimmer, at 219-215, requiring cooperation of Democratic lawmakers and the Biden administration. What happens when the government shuts down? Some agencies are able to continue operations in the event of a funding lapse. Air travel is unlikely to face immediate interruptions because key federal workers are considered "essential," but some work on permits, agricultural and import data, and regulations could be curtailed. The US Federal Energy Regulatory Commission has funding to get through a "short-term" shutdown but could be affected by a longer shutdown, chairman Willie Phillips said. The US Department of Energy, which includes the Energy Information Administration and its critical energy data provision services, expects "no disruptions" if funding lapses for 1-5 days, according to its shutdown plan. The US Environmental Protection Agency would furlough about 90pc of its nearly 17,000 staff in the event of a shutdown, according to a plan it updated earlier this year. The Interior Department's shutdown contingency plan calls for the Bureau of Land Management (BLM) to furlough 4,900 out of its nearly 10,000 employees. BLM, which is responsible for permitting oil, gas and coal activities on the US federal land, would cease nearly all functions other than law enforcement and emergency response. Interior's Bureau of Safety and Environmental Enforcement, which oversees offshore leases, would continue permitting activities but would furlough 60pc of its staff after its funding lapses. The US Bureau of Ocean Energy Management will keep processing some oil and gas exploration plans with an on-call group of 40 exempted personnel, such as time-sensitive actions related to ongoing work. The shutdown also affects multiple other regulatory and permitting functions across other government agencies, including the Departments of Agriculture, Transportation and Treasury. By Haik Gugarats Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Australia’s Cleanaway, LMS to produce landfill gas


24/12/20
24/12/20

Australia’s Cleanaway, LMS to produce landfill gas

Sydney, 20 December (Argus) — Australian waste management operator Cleanaway and bioenergy firm LMS Energy will partner on a 22MW landfill gas-fired power station at Cleanaway's Lucas Heights facility near the city of Sydney. Cleanaway, Australia's largest publicly listed waste management firm, will receive exclusive rights to landfill gas produced at Lucas Heights for 20 years, the company said on 20 December. LMS will invest A$46mn ($29mn) in new bioelectricity assets, including a 22MW generator. Tightening gas markets owing to underinvestment in new supply has led to speculation that more waste-to-energy plants could be brought on line in coming years, especially in the southern regions. Landfill gas projects receive Australian Carbon Credit Units (ACCUs) by avoiding methane releases, with the total ACCU quantity calculated after a default baseline of 30pc is deducted for projects beginning after 2015. A total of 42.6mn ACCUs were issued to landfill gas projects since the start of the ACCU scheme in 2011, 27pc of the total 155.7mn and the second-largest volume after human-induced regeneration (HIR) methods at 46.68mn. Canberra is reviewing ACCU issuance for these projects, and wants most projects to directly measure methane levels in captured landfill gas to avoid overestimation. Landfill gas operations which generate electricity from the captured gases can also receive large-scale generation certificates (LGCs). LMS has 70 projects currently registered at the Clean Energy Regulator (CER) and has received 24.57mn ACCUs since the start of the scheme. This is the largest volume for any single project proponent, just ahead of Australian environmental market investor GreenCollar's subsidiary Terra Carbon with 23.57mn units. Cleanaway received almost 1mn ACCUs from two projects and has four other projects that have yet to earn ACCUs. By Tom Major and Juan Weik Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Trump backs new deal to avoid shutdown: Update


24/12/19
24/12/19

Trump backs new deal to avoid shutdown: Update

Adds updates throughout Washington, 19 December (Argus) — US president-elect Donald Trump is offering his support for a rewritten spending bill that would avoid a government shutdown but leave out a provision authorizing year-round 15pc ethanol gasoline (E15) sales. The bill — which Republicans rewrote today after Trump attacked an earlier bipartisan agreement — would avoid a government shutdown starting Saturday, deliver agricultural aid and provide disaster relief. Trump said the bill was a "very good deal" that would also include a two-year suspension of the "very unnecessary" ceiling on federal debt, until 30 January 2027. "All Republicans, and even the Democrats, should do what is best for our Country, and vote 'YES' for this Bill, TONIGHT!" Trump wrote in a social media post. Passing the bill would require support from Democrats, who are still reeling after Trump and his allies — including Tesla chief executive Elon Musk — upended a spending deal they had spent weeks negotiating with US House speaker Mike Johnson (R-Louisiana). Democrats have not yet said if they would vote against the new agreement. "We are prepared to move forward with the bipartisan agreement that we thought was negotiated in good faith with House Republicans," House minority leader Hakeem Jeffries (D-New York) said earlier today. That earlier deal would have kept the government funded through 14 March, in addition to providing a one-year extension to the farm bill, $100bn in disaster relief and $10bn in aid for farmers. The bill would also provide a waiver that would avoid a looming ban on summertime sales of E15 across much of the US. Ethanol industry officials said they would urge lawmakers to vote against any package without the E15 provision. "Pulling E15 out of the bill makes absolutely no sense and is an insult to America's farmers and renewable fuel producers," Renewable Fuels Association chief executive Geoff Cooper said. If no agreement is reached by Friday at 11:59pm ET, federal agencies would have to furlough millions of workers and curtail services, although some agencies are able to continue operations in the event of a short-term funding lapse. Air travel is unlikely to face immediate interruptions because key federal workers are considered "essential," but some work on permits, agricultural and import data, and regulations could be curtailed. The US Federal Energy Regulatory Commission has funding to get through a "short-term" shutdown but could be affected by a longer shutdown, chairman Willie Phillips said. The US Department of Energy expects "no disruptions" if funding lapses for 1-5 days, according to its shutdown plan. The US Environmental Protection Agency would furlough about 90pc of its nearly 17,000 staff in the event of a shutdown, according to a plan it updated earlier this year. By Chris Knight Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.