Australian hydrogen developer Infinite Green Energy (IGE) has entered administration the day before an application for a winding up order was due to be heard before the Western Australian (WA) state Supreme Court, filings show.
IGE had been fighting an application filed by plaintiff DD Investment WA, a privately-owned company, to appoint liquidators because of unpaid debts. The firm entered administration on 7 April, financial regulator Australian Securities and Investments Commission filings show.
The company's Arrowsmith project in WA was supposed to produce 23 t/d of green hydrogen with stage 1 of its scheme, at a rural site about 290km north of state capital Perth. The project's focus was developing fuel for the transport sector, with a final fortnight-long public consultation period for its environmental impact assessment scheduled to close on 12 April, according to the WA government.
IGE's plans included a 100MW alkaline electrolyser and 40 t/d liquefaction system with first output in late 2027-28. It would later scale up to 42 t/d in stage 2, the developer said, with South Korean engineering company Samsung C&T backing plans in 2023 for an eventual 100,000 t/yr of production.