CHS approves $3bn Spiritwood nitrogen plant
CHS will proceed with construction of a proposed nitrogen fertilizer plant in Spiritwood, North Dakota, and plans for the facility to be operational in the first half of 2018.
The plant will produce more than 2,400 st/day (876,000 st/yr) gross ammonia which will be upgraded to urea, UAN and diesel exhaust fluid (DEF). The farmer-owned cooperative plans on primarily serving agricultural retailers within a 200-mile radius, including the Dakotas and parts of Minnesota, Montana and Canada.
CHS estimates the cost of the project at $3bn, up from initial projections of $1.5bn-2bn. The rise in capital expenditure caused the company to put the project on hold in April. CHS attributed the higher-than-expected cost to increased construction costs, likely owing to labor constraints in a state that has seen a boom in oil/gas shale development.
"Because of the size and scale of this investment, we needed to take the additional time to review costs and reassess areas where we could make modifications," CHS chief executive Carl Casale said. "We are now fully prepared to proceed with an investment that will add tremendous value to our member-owners, and further expand our global crop nutrients business platform."
Final plans for the project were approved by CHS' board of directors this week. Groundbreaking will take place after additional details are ironed out, CHS said.
CHS said it will be the lone investor for the project, which it called the "single largest private investment project ever undertaken in North Dakota." CHS is awaiting approval of its application for a $1bn Advanced Fossil Energy loan from the US Department of Energy. The company said the application is still in the first phase of review.
The plant will be served by the new 95-mile (153km) Wind Ridge natural gas pipeline built by WBI Energy.
Spiritwood is the second planned North Dakota urea plant to be approved. Dakota Gasification is currently building a $402mn, 1,100 st/day urea (401,500 st/yr) plant at its existing Great Plains Synfuels Plant in Beulah, North Dakota, that already produces 400,000 st/yr ammonia and 105,000 st/yr ammonium sulfate. Urea production is expected to begin in early 2017.
bh/dcb
Send comments to feedback@argusmedia.com
If you would like to review other ArgusMedia.com content options, request more information about Argus' energy news, data and analysis services.
Copyright © 2014 Argus Media Ltd - www.ArgusMedia.com - All rights reserved.
Related news posts
India's Fact seeks 40,000t of 15-15-15 in tender
India's Fact seeks 40,000t of 15-15-15 in tender
London, 26 July (Argus) — Indian fertilizer importer Fact has issued a tender to buy two 20,000t lots of 15-15-15. The tender will close on 9 August, and Fact intends to open offers on the same day. The importer requests delivery of one cargo to Kakinada and the other to Tuticorin, both on India's east coast. In both cases, Fact seeks a laycan at the discharge ports of 15-31 October. In late May, Fact bought two 30,000t lots of 15-15-15 against a tender , paying $342/t cfr duty unpaid, with credit terms of 30 days, for Russian product. Prices around the latest tender will be higher, following a firming of the market. Fact's request marks the second major Indian tender for complex fertilizers this week, after fellow importer HURL requested 30,000t lots of 20-20-0+13S . By David Maher Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.
Australia’s Ichthys LNG to restart liquefaction train
Australia’s Ichthys LNG to restart liquefaction train
Singapore, 26 July (Argus) — The second liquefaction train at Australia's 9.3mn t/yr Ichthys LNG export terminal plans to resume partial operations today, after going off line unexpectedly during 18-19 July, according to traders. The export facility is operated by Japanese upstream firm Inpex. Repairs at the affected train could take up to a month before it returns to full production, although the train is expected to restart by this weekend, according to market participants. Attempts to restart train two could take place by 26 July. Some delays to deliveries from the facility are expected, although there are also unconfirmed reports that up to two cargoes may have already been cancelled at the time of writing. The overall impact on the market is likely to be limited for now, with continuing weak spot demand from northeast Asian importers. Some term buyers previously requested for their deliveries to be deferred, traders said, although it is unclear just how many requests for deferment were received. But other participants have pointed out that the winter restocking season could soon start and any further impediments to train two's restart could lift prices. Recent temperatures in Japan have been higher than expected, with at least a 70pc probability of above-normal temperatures over the vast majority of the country until 23 August, according to the latest forecast issued by the Japan Meteorological Agency on 25 July. At least one Japanese utility may be considering spot purchases for August, owing to higher-than-expected power consumption because of warmer temperatures. But at least two other Japanese firms could be looking to sell a September and an October cargo each, traders said, which could indicate that the spot market is still sufficiently well-supplied to cope with additional demand from Japanese utilities. The 174,000m³ Grace Freesia departed from Ichthys on 25 July after loading an LNG cargo, according to ship tracking data from Kpler. The export terminal sold a spot cargo for loading over 2-6 June at around high-$9s/mn Btu through a tender that closed on 10 May, but further details are unclear. The US' 17.3mn t/yr Freeport export terminal also faced issues restarting since it was first taken off line on 7 July as a precautionary measure against Hurricane Beryl. The terminal loaded its first cargo on 21 July . All three trains are likely to be back on line as of 26 July, although production at the facility should still be closely monitored, traders said. By Naomi Ong Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.
Australia’s Empire Energy signs deal to sell gas to NT
Australia’s Empire Energy signs deal to sell gas to NT
Adelaide, 26 July (Argus) — Australian independent Empire Energy has signed an agreement to supply the Northern Territory (NT) with gas from its Carpentaria project in the onshore Beetaloo subbasin. Empire will supply NT with up to 25 TJ/d (668,000 m³/d) of gas over 10 years, starting from mid-2025. This equates to an estimated total supply of 75PJ (2bn m3) of gas. The deal includes scope for an additional 10 TJ/d for up to 10 years if production level at the Carpentaria plant exceeds 100 TJ/d. The firm bought domestic utility AGL Energy's dormant 42 TJ/d Rosalind Park gas plant late last yearwith plans to reassemble the facility on site at Carpentaria, subject to a final investment decision on the project. Gas will be delivered to the NT government-owned Power and Water (PWC) via the McArthur River gas pipeline on an ex-field take-or-pay basis, Empire said on 26 July. PWC in April signed an agreement to buy 8.6PJ of gas from Australian independent Central Petroleum , to supply gas-fired power generation and private-sector customers. Low production at Italian energy firm Eni's Blacktip field, offshore the NT, has led PWC to court new supply while providing a new outlet for prospective producers operating within Beetaloo. The largest Beetaloo acreage holder, Tamboran Resources, has revealed ambitious plans for a 6.6mn t/yr LNG plant to be located near Darwin Harbour's two existing LNG projects, using the basin's shale gas resources as feedstock. By Tom Major Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.
BayWa suspends 2024 profit forecast over restructuring
BayWa suspends 2024 profit forecast over restructuring
London, 25 July (Argus) — German agricultural group BayWa on Wednesday suspended its full-year profit forecast due on 8 August, citing ongoing restructuring. It posted a preliminary revenue of €10.7bn ($11.6bn) for the first half of the year, down by 15pc from €12.6bn a year ago. BayWa's first-half 2024 preliminary earnings before interest, tax, depreciation and amortisation stood at €149.5mn, less than half of the €322.1mn earned in the same period last year. BayWa said it continues to be in constructive talks with its financing partners, adding that it also has postponed publication of the final half-yearly results to 27 September, citing impairment reviews. The company commissioned a restructuring report on 12 July in response to a "strained financing situation". The Munich-headquartered BayWa Group operates in the fields of energy, agriculture — including fertilizers — and building materials. By Suzie Skipper Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.
Business intelligence reports
Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.
Learn more