A group of Europe's gas system operators have substantially expanded a proposal to build a continent-wide hydrogen network using repurposed natural gas pipelines and new infrastructure.

Industry association European Hydrogen Backbone (EHB) has proposed building a 11,600km hydrogen transportation network by 2030, which would expand to 39,700km across 21 European countries by 2040. This is enlarged from last year's proposal for a 6,800km network by 2030 and 23,000km by 2040, connecting 10 European countries.

The previous plan was concentrated in the Netherlands, Germany, Belgium and France, but the newly-proposed network widens the project's reach to the UK and Ireland, much of central and eastern Europe, Finland, Estonia and Greece.

About 69pc of the proposed network would consist of repurposed existing natural gas infrastructure, with the remainder consisting of newly-built pipelines used to connect new offtakers and located in countries with small gas grids, EHB said. This is down from 75pc in the previous version of the proposal. A dedicated network is needed to integrate planned renewable electricity generation and to develop a liquid cross-border hydrogen market, EHB said (see planned pipelines table).

The network would eventually incorporate major existing gas infrastructure, including salt caverns and aquifer storage sites across the continent (see country-level table).

BBL or Interconnector to link UK

The UK's network would be connected to mainland Europe by retrofitting the Interconnector — which connects to Belgium — or the BBL, which connects to the Netherlands. And one of the two pipelines connecting Ireland and the UK at Moffat could be converted to carry hydrogen. The plan foresees four of the UK's five major industrial hubs connected to hydrogen production clusters by 2030 through a phased re-purposing of existing infrastructure.

EHB also proposed converting a number of pipelines that connect EU markets with gas exporters, including at least one of the five parallel lines that compose the Transmed route which connects Italy and Libya, the two undersea connections between Algeria and Spain, one of the pipelines used to deliver Norwegian gas to mainland Europe and the Trans-Adriatic Pipeline (Tap) — which only started up this year and delivers Azeri gas sent to Europe through Turkey. But this would likely require suppliers to produce hydrogen domestically for delivery to Europe, either through steam reformation of methane or through electrolysis, primarily powered by renewable electricity sources.

Major existing gas transit routes are also included in the proposal. The large-diameter Tag pipeline passing to Italy from Slovakia as well as connections through the Czech Republic and Slovakia could be repurposed if gas flows "drop significantly", freeing up one of two parallel lines, EHB said.

A "much more dynamic picture" has emerged for Germany compared with the previous proposal, the association said. Natural gas and hydrogen may compete for the same pipeline infrastructure by 2035, with decisions to depend largely on political support for the scale-up of hydrogen and general market developments of hydrogen and natural gas, EHB said.

Some operators mentioned Russia as a possible hydrogen source. The country yesterday said it plans to achieve a 20-25pc share of global hydrogen trading by 2035.

The proposal also incorporates new infrastructure, including hydrogen produced by excess renewables output on "energy islands" offshore the Netherlands, Germany and Denmark and a new subsea pipeline connecting Germany, Sweden, Finland and Estonia.

The expanded network would allow pipeline imports from Europe's eastern and southern neighbours — including Ukraine — as well as imports of liquid hydrogen at Europe's main ports, EHB said. And extending the network through central and eastern Europe would allow renewables to play a larger role in a largely coal-based power mix and enable hydrogen to decarbonise heavy industry concentrated in the region.

But the design of the network and timeline depend on market conditions for hydrogen and gas, as well as the introduction of a "stable hydrogen framework", the group said. Hydrogen supply and demand and its increasing integration in the energy system may lead to alternative or additional routes, as well as a shift in the timeline forward or backward, EHB said.

Investment costs down, transport costs up

The envisaged hydrogen network by 2040 would cost €43bn-81bn, EHB said. While up from the €27bn-64bn previously anticipated, the cost per kilometre is lower as the proposal now incorporates smaller diameter pipelines which are cheaper to repurpose.

But smaller diameter pipelines have higher operating costs, increasing the average transport cost to €0.11-0.21/kg hydrogen. This is attractive and cost-effective for long-distance transportation, taking into account an estimated future production cost of €1-2/kg, EHB said (see investment costs, project costs tables).

Country-level, selected proposed H₂ commitments
CountryEmission commitments / H₂ plans or possible outcomes
AustriaBy 2030, 100pc renewable electricity
By 2030, blending to/from existing cross-border infrastructure
By 2035, bi-directional repurposing of one TAG string
By 2040, additional interconnector to Germany for Ukrainian H₂
By 2040, carbon neutrality
BelgiumBy 2040, demand expected to exceed production
Czech RepublicBy 2035, possible transit to Germany from Slovakia
By 2035, possible transit to Germany from Germany via Gazelle pipeline
DenmarkBy 2030, 70pc emisssions reduction
In 2030, two "energy islands" of 2GW each
In 2030, 3GW electrolysis capacity
By 2040, one island expanded to 10GW, offshore H₂ production
FranceIn 2030, 6.5GW electrolysis capacity
By 2040, "mature" network with three interconnectors with Spain
Most pipelines would be repurposed
GermanyIn 2030, H₂ demand of 90-110TWh
Imports from Netherlands, Czech Republic
UKBy 2030, 5GW H₂ production capacity
By 2030, 40GW offshore wind capacity
By 2030, four low-carbon industrial clusters
By 2035, all five industrial clusters potentially connected
By 2040, repurposed connection to Ireland
Most pipelines would be repurposed
GreeceBy 2040, two main industrial clusters connected by new H₂ pipelines
Plans for 7GW of wind capaciy and 8GW of solar capacity
Possible export connection via TAP or south-east Europe
HungaryBy 2030, 6GW solar capacity
By 2035, possibility of mature work with six interconnections
By 2035, a transit country for Ukrainian H₂
By 2050, carbon neutrality
IrelandBy 2030, 5GW offshore wind capacity
By 2040, reconfiguration of Dublin gas network
ItalyBy 2030, repurposing of pipelines enabling import via Tunisia
By 2035, onward connnection to Austria, Slovenia
By 2040, possible interconnection with Switzerland
NetherlandsBy 2027, first 'backbone' of repurposed pipelines available
By 2030, 10-15GW network capacity
By 2050, 180GW offshore wind capacity
PolandBy 2030, 2GW electrolyser capacity
By 2030, 5.9GW offshore wind capacity
By 2040, 11GW offshore wind capacity
Post 2040, all industrial clusters connected
Repurposing of existing pipelines difficult due to gas demand projections
SlovakiaTransit market for Ukrainian-sourced supply
By 2035, repurposing of one existing pipeline from Ukraine
SpainBy 2030, 4GW electrolyser capacity
Long-term H₂ production and supply ambition
By 2035, connection to France, north Africa
By 2040, additional connection to France
Estimated project costs
Cost scenarios
CapexLowMediumHigh
Pipeline capex (small, new)€mn/km1.41.51.8
Pipeline capex (medium, new)€mn/km2.02.22.7
Pipeline capex (large, new)€mn/km2.52.83.4
Pipeline capex (small, repurposed)€mn/km0.20.30.5
Pipeline capex (medium, repurposed)€mn/km0.20.40.5
Pipeline capex (large, repurposed)€mn/km0.30.50.6
Compressor station capex€mn/MWe2.23.46.7
Assumptions
Weighted average cost of capital%5-75-75-7
Operations and maintenance (ex. electricity)€/yr as % of capex0.8-1.70.8-1.70.8-1.7
Electricity price€/MWh405090
Depreciation (pipelines)yrs30-5530-5530-55
Depreciation (compressor stations)yrs15-3315-3315-33
Planned hydrogen infrastructure, EHB*km
RepurposedNew
Pipeline diameter
Small (<28in, <700mm)3,172.01,586.0
Medium (28-37in, 700-950mm)11,498.55,154.5
Large (>37in, >950mm)12,688.05,551.0
Total27,200.012,450.0
*Total differs from elements due to rounding
European Hydrogen Backbone costs, 2040 bn
LowMediumHigh
Pipeline cost33.041.051.0
Compression cost10.015.030.0
Total investment cost43.056.081.0
Operational expenditure (/yr)0.81.11.8
Electricity costs (/yr)0.91.12.0
Total operatonal cost1.72.23.8

Sharelinkedin-sharetwitter-sharefacebook-shareemail-share

Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

News
26/07/24

Eni confident on 2024 output, but Libya project slips

Eni confident on 2024 output, but Libya project slips

London, 26 July (Argus) — Executives at Italy's Eni are confident it will achieve the upper end of its 1.69mn-1.71mn production guidance for this year, but start-up of a key Libyan project is set to slip from 2026 into 2027. In a presentation of second-quarter earnings today, A&E Structure was one of two Libyan projects on a list of Eni's upcoming start-ups through to 2028 that will deliver some 740,000 b/d of oil equivalent (boe/d) of net production to the company. A&E Structure is a 160,000 boe/d gas development that will include some 40,000 b/d of liquids production, mainly condensate. A&E Structure is central to Libya's ability to sustain gas exports to Italy, which have dropped in recent years on a combination of rising domestic consumption and falling production. Supplies through the 775mn ft³/d Greenstream pipeline hit their lowest since the 2011 revolution in 2023, averaging 250mn ft³/d. The slide has continued since, with year-to-date volumes of around 160mn ft³/d on track for a record low. Eni's other upcoming Libyan project — the Bouri Gas Utilisation Project development that aims to capture 85mn ft³/d of gas at the 25,000 b/d offshore Bouri oil field — had already been pushed back from 2025 to 2026. For 2024 Eni expects to be "at the upper boundary of its guidance", according to chief operating officer of Natural Resources Guido Brusco. The company had a strong first half, during which output was 1.73mn boe/d — 5pc up on the year — thanks to good performance at assets in Ivory Coast, Indonesia, Congo (Brazzaville) and Libya. Brusco said Eni is in the process of starting up its 30,000 boe/d Cassiopea gas project in Italy, with first production expected next month, and the 45,000 b/d second phase of the Baleine oil project in Ivory Coast is expected to start by the end of this year. At Baleine, Brusco confirmed the two vessels to be used at phase two "will be in country in September and, building on the experience of phase one, we expect a couple of months of final integrated commissioning" before first oil. Eni also said today it would raise its dividend for 2024 by 6pc over 2023 to €1/share, and confirmed share repurchases this year of €1.6bn. It said there is potential for an additional buyback of up to €500mn, which is being evaluated this quarter. Eni's debt gearing is scheduled to fall below 20pc by the end of the year. Chief financial officer Francesco Gattei said these accelerated share buybacks would be possible if divestment deals are confirmed. By Jon Mainwaring and Aydin Calik Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Find out more
News

Australia’s Ichthys LNG to restart liquefaction train


26/07/24
News
26/07/24

Australia’s Ichthys LNG to restart liquefaction train

Singapore, 26 July (Argus) — The second liquefaction train at Australia's 9.3mn t/yr Ichthys LNG export terminal plans to resume partial operations today, after going off line unexpectedly during 18-19 July, according to traders. The export facility is operated by Japanese upstream firm Inpex. Repairs at the affected train could take up to a month before it returns to full production, although the train is expected to restart by this weekend, according to market participants. Attempts to restart train two could take place by 26 July. Some delays to deliveries from the facility are expected, although there are also unconfirmed reports that up to two cargoes may have already been cancelled at the time of writing. The overall impact on the market is likely to be limited for now, with continuing weak spot demand from northeast Asian importers. Some term buyers previously requested for their deliveries to be deferred, traders said, although it is unclear just how many requests for deferment were received. But other participants have pointed out that the winter restocking season could soon start and any further impediments to train two's restart could lift prices. Recent temperatures in Japan have been higher than expected, with at least a 70pc probability of above-normal temperatures over the vast majority of the country until 23 August, according to the latest forecast issued by the Japan Meteorological Agency on 25 July. At least one Japanese utility may be considering spot purchases for August, owing to higher-than-expected power consumption because of warmer temperatures. But at least two other Japanese firms could be looking to sell a September and an October cargo each, traders said, which could indicate that the spot market is still sufficiently well-supplied to cope with additional demand from Japanese utilities. The 174,000m³ Grace Freesia departed from Ichthys on 25 July after loading an LNG cargo, according to ship tracking data from Kpler. The export terminal sold a spot cargo for loading over 2-6 June at around high-$9s/mn Btu through a tender that closed on 10 May, but further details are unclear. The US' 17.3mn t/yr Freeport export terminal also faced issues restarting since it was first taken off line on 7 July as a precautionary measure against Hurricane Beryl. The terminal loaded its first cargo on 21 July . All three trains are likely to be back on line as of 26 July, although production at the facility should still be closely monitored, traders said. By Naomi Ong Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Australia’s Empire Energy signs deal to sell gas to NT


26/07/24
News
26/07/24

Australia’s Empire Energy signs deal to sell gas to NT

Adelaide, 26 July (Argus) — Australian independent Empire Energy has signed an agreement to supply the Northern Territory (NT) with gas from its Carpentaria project in the onshore Beetaloo subbasin. Empire will supply NT with up to 25 TJ/d (668,000 m³/d) of gas over 10 years, starting from mid-2025. This equates to an estimated total supply of 75PJ (2bn m3) of gas. The deal includes scope for an additional 10 TJ/d for up to 10 years if production level at the Carpentaria plant exceeds 100 TJ/d. The firm bought domestic utility AGL Energy's dormant 42 TJ/d Rosalind Park gas plant late last yearwith plans to reassemble the facility on site at Carpentaria, subject to a final investment decision on the project. Gas will be delivered to the NT government-owned Power and Water (PWC) via the McArthur River gas pipeline on an ex-field take-or-pay basis, Empire said on 26 July. PWC in April signed an agreement to buy 8.6PJ of gas from Australian independent Central Petroleum , to supply gas-fired power generation and private-sector customers. Low production at Italian energy firm Eni's Blacktip field, offshore the NT, has led PWC to court new supply while providing a new outlet for prospective producers operating within Beetaloo. The largest Beetaloo acreage holder, Tamboran Resources, has revealed ambitious plans for a 6.6mn t/yr LNG plant to be located near Darwin Harbour's two existing LNG projects, using the basin's shale gas resources as feedstock. By Tom Major Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Refining, LNG segments take Total’s profit lower in 2Q


25/07/24
News
25/07/24

Refining, LNG segments take Total’s profit lower in 2Q

London, 25 July (Argus) — TotalEnergies said today that a worsening performance at its downstream Refining & Chemicals business and its Integrated LNG segment led to a 7pc year-on-year decline in profit in the second quarter. Profit of $3.79bn was down from $5.72bn for the January-March quarter and from $4.09bn in the second quarter of 2023. When adjusted for inventory effects and special items, profit was $4.67bn — slightly lower than analysts had been expecting and 6pc down on the immediately preceding quarter. The biggest hit to profits was at the Refining & Chemicals segment, which reported an adjusted operating profit of $639mn for the April-June period, a 36pc fall on the year. Earlier in July, TotalEnergies had flagged lower refining margins in Europe and the Middle East, with its European Refining Margin Marker down by 37pc to $44.9/t compared with the first quarter. This margin decline was partially compensated for by an increase in its refineries' utilisation rate: to 84pc in April-June from 79pc in the first quarter. The company's Integrated LNG business saw a 13pc year on year decline in its adjusted operating profit, to $1.15bn. TotalEnergies cited lower LNG prices and sales, and said its gas trading operation "did not fully benefit in markets characterised by lower volatility than during the first half of 2023." A bright spot was the Exploration & Production business, where adjusted operating profit rose by 14pc on the year to $2.67bn. This was mainly driven by higher oil prices, which were partially offset by lower gas realisations and production. The company's second-quarter production averaged 2.44mn b/d of oil equivalent (boe/d), down by 1pc from 2.46mn boe/d reported for the January-March period and from the 2.47mn boe/d average in the second quarter of 2023. TotalEnergies attributed the quarter-on-quarter decline to a greater level of planned maintenance, particularly in the North Sea. But it said its underlying production — excluding the Canadian oil sands assets it sold last year — was up by 3pc on the year. This was largely thanks to the start up and ramp up of projects including Mero 2 offshore Brazil, Block 10 in Oman, Tommeliten Alpha and Eldfisk North in Norway, Akpo West in Nigeria and Absheron in Azerbaijan. TotalEnergies said production also benefited from its entry into the producing fields Ratawi, in Iraq, and Dorado in the US. The company expects production in a 2.4mn-2.45mn boe/d range in the third quarter, when its Anchor project in the US Gulf of Mexico is expected to start up. The company increased profit at its Integrated Power segment, which contains its renewables and gas-fired power operations. Adjusted operating profit rose by 12pc year-on-year to $502mn and net power production rose by 10pc to 9.1TWh. TotalEnergies' cash flow from operations, excluding working capital, was $7.78bn in April-June — an 8pc fall from a year earlier. The company has maintained its second interim dividend for 2024 at €0.79/share and plans to buy back up to $2bn of its shares in the third quarter, in line with its repurchases in previous quarters. By Jon Mainwaring Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Repsol 2Q profit doubles but cash flow turns negative


24/07/24
News
24/07/24

Repsol 2Q profit doubles but cash flow turns negative

Madrid, 24 July (Argus) — Spanish integrated Repsol's profit more than doubled on the year in the second quarter, as lower one-time losses and better results in the upstream and customer divisions more than offset a weaker refining performance. But its cash flow turned negative as it completed the buyout of its UK joint venture with China's state-controlled Sinopec, raised investments and experienced weaker refining margins. Net debt was sharply higher, largely reflecting share buy-backs. Repsol has said it will acquire and cancel a further 20mn of its own shares before the end of the year, which will probably further increase its debt. It completed a 40mn buy-back in the first half of the year. Repsol's profit climbed to €657mn ($714mn) in April-June from €308mn a year earlier, when earnings were hit by a large provision against an arbitration ruling that obliged it to acquire Sinopec's stake in their UK joint venture. Excluding this and other special items, such as a near threefold reduction in the negative inventory effect to €85mn, Repsol's adjusted profit increased by 4pc on the year to €859mn. Repsol confirmed the fall in refining margins and upstream production reported earlier in July . Liquids output increased by 3pc on the year to 214,000 b/d, and gas production fell by 4pc to 2.1bn ft³/d. Adjusted upstream profit increased by 4pc on the year to €427mn. The higher crude production and a 13pc rise in realised prices to $78.6/bl more than offset lower gas production and prices, which fell by 6pc to $3.1/'000 ft³ over the same period. Adjusted profit at Repsol's industrial division — which includes 1mn b/d of Spanish and Peruvian refining capacity, an olefins-focused petrochemicals division, and a gas and oil product trading business — was down by 16pc on the year at €288mn. Profit fell at the 117,000 b/d Pampilla refinery in Peru after a turnaround and weak refining margins, and there was lower income from gas trading. Spanish refining profit rose on a higher utilisation rate and gains in oil product trading. Repsol's customer-focused division reported adjusted profit of €158mn in April-June, 7pc higher on the year thanks to higher retail electricity margins, a jump in sales from an expanded customer base, higher margins in aviation fuels and higher sales volumes in lubricants. Repsol swung to a negative free cash flow, before shareholder remuneration and buy-backs, of €574mn in the second quarter, from a positive €392mn a year earlier. After shareholder remuneration, including the share buy-backs and dividends, Repsol had a negative cash position of €1.12bn compared with a positive €133mn a year earlier. Repsol's net debt more than doubled to €4.595bn at the end of June from €2.096bn on 31 December 2023, reflecting the share buy-backs and new leases of equipment. By Jonathan Gleave Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Generic Hero Banner

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more