Latest market news

Baltic April gas consumption rises on year

  • Market: Electricity, Natural gas
  • 08/05/24

Gas demand in the three Baltic states and Finland was up by 26pc on the year in April, although there were diverging trends in the different markets.

Consumption in Finland, Estonia, Latvia and Lithuania totalled 3.56TWh, up from 2.82TWh a year earlier but down from 4.31TWh in March (see data and download, graph). That said, total demand was still well below the 2018-21 average for the month of 5.03TWh.

Consumption was up on the year in all three Baltic countries, but Finnish demand edged down. This was the first month in which Finnish demand was lower on the year since April 2023. In contrast, Lithuanian consumption surged by nearly 50pc on the year, and was also higher than in February and March despite the end of the traditional heating season.

Gas-fired power generation held broadly stable from a year earlier, totalling 305MW across the four countries compared with 301MW in April last year (see gas-fired output table). Output edged down in Estonia and Lithuania and dropped by 25MW in Finland, but this was offset by a 31MW increase on the year in Latvia. But, unlike in March, gas-fired output fell by 246MW, a large contributing factor to the lower gas demand on the month. Many combined heat and power plants will have switched off at around the end of March or mid-April as the traditional heating season came to a close, possibly driving the fall in gas-fired output. But renewables generation was also stronger in April than March, particularly in Finland, where wind output rose to 2.03GW from 1.63GW, while hydro also stepped up. In Lithuania, solar and waste-based production increased on the month.

Demand was also stronger despite higher year-on-year minimum temperatures in all four capital cities, which may have curbed most residual heating demand after the end of the traditional heating season, although there was a brief cold snap towards the middle of the month that temporarily drove up demand (see temperatures table).

With gas-fired power generation only marginally higher than a year earlier, and the warmer weather curbing residential demand, a possible uptick in industrial demand may have driven the aggregate rise in consumption.

Average prices on the regional GET Baltic exchange were €33.30/MWh in April, up by 8pc on the month but 30pc lower than a year earlier, the exchange said. Prices increased in around the middle of April "due to the unexpectedly cold weather and the increased demand for gas in the market", but then fell again "as the weather warmed", GET Baltic chief executive Giedre Kurme said. There were a total of 2,400 transactions last month for a combined 642GWh of gas. Volumes sold on the Finnish market accounted for 42pc, the joint Latvian-Estonian market 33pc, and the remaining 25pc was sold in Lithuania.

Klaipeda and Balticconnector to change flows

The return of the Finnish-Estonian Balticconnector pipeline and the start of maintenance at the Klaipeda LNG terminal in Lithuania will drive changed flow patterns this month.

The Balticconector resumed commercial operations on 22 April after being off line since 8 October following a rupture caused by a dragging ship anchor. The reconnection of Finland to its southern neighbours has allowed for strong southward flows since 22 April, at an average of 62 GWh/d on 22 April-7 May.

Some of this gas is probably being injected into storage, with the region's only facility at Incukalns switching to net injections on 23 April from net withdrawals of 7 GWh/d earlier in the month. Net injections have since averaged 46 GWh/d on 23 April-6 May, the latest data from EU transparency body GIE show. Stocks at Incukalns ended the withdrawal season on 30 April at 11.29TWh, the highest since at least 2014 and well above the previous high from last year of 9.03TWh. Large volumes of gas that had been stored over the previous summer for export to Finland over the winter were left stranded in Incukalns after the Balticconnector went off line.

And the Klaipeda LNG terminal began maintenance on 1 May, which will last until 15 June, as the terminal's Independence floating storage and regasification unit (FSRU) departed for dry-docking in Denmark. As a result, there were net exports from Poland to Lithuania for the first time since early November, at an average of 17 GWh/d on 1-7 May. Some of this gas could have been withdrawn from Ukrainian storage, with flows from Ukraine to Poland averaging 10 GWh/d over the same period. Lithuania's largest supplier Ignitis has said it stored some volumes in Ukraine. And flows at the Kiemenai border point with Latvia have also flipped towards Lithuania, averaging 11 GWh/d on 1-7 May, compared with net flows towards Latvia of 15 GWh/d in April. That said, there were no flows at the point on 6-26 April.

Finnish, Baltic average gas-fired power generationMW
Apr-24Apr-23Mar-24± Apr 23± Mar 24
Estonia567-1-2
Latvia491821531-166
Lithuania464752-1-6
Finland205230277-25-72
Total3053015514-246
Daily average minimum temperature in FinBalt capitals°C
Apr-24Apr-23Mar-24± yr/yr± m/m2014-23 Apr avg
Vilnius5.223.830.931.394.292.63
Riga5.014.981.930.033.083.65
Tallinn2.001.46-0.590.542.591.17
Helsinki0.11-0.45-2.550.562.660.12

Finnish and Baltic April consumption by country GWh

Sharelinkedin-sharetwitter-sharefacebook-shareemail-share

Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

News
26/07/24

Eni confident on 2024 output, but Libya project slips

Eni confident on 2024 output, but Libya project slips

London, 26 July (Argus) — Executives at Italy's Eni are confident it will achieve the upper end of its 1.69mn-1.71mn production guidance for this year, but start-up of a key Libyan project is set to slip from 2026 into 2027. In a presentation of second-quarter earnings today, A&E Structure was one of two Libyan projects on a list of Eni's upcoming start-ups through to 2028 that will deliver some 740,000 b/d of oil equivalent (boe/d) of net production to the company. A&E Structure is a 160,000 boe/d gas development that will include some 40,000 b/d of liquids production, mainly condensate. A&E Structure is central to Libya's ability to sustain gas exports to Italy, which have dropped in recent years on a combination of rising domestic consumption and falling production. Supplies through the 775mn ft³/d Greenstream pipeline hit their lowest since the 2011 revolution in 2023, averaging 250mn ft³/d. The slide has continued since, with year-to-date volumes of around 160mn ft³/d on track for a record low. Eni's other upcoming Libyan project — the Bouri Gas Utilisation Project development that aims to capture 85mn ft³/d of gas at the 25,000 b/d offshore Bouri oil field — had already been pushed back from 2025 to 2026. For 2024 Eni expects to be "at the upper boundary of its guidance", according to chief operating officer of Natural Resources Guido Brusco. The company had a strong first half, during which output was 1.73mn boe/d — 5pc up on the year — thanks to good performance at assets in Ivory Coast, Indonesia, Congo (Brazzaville) and Libya. Brusco said Eni is in the process of starting up its 30,000 boe/d Cassiopea gas project in Italy, with first production expected next month, and the 45,000 b/d second phase of the Baleine oil project in Ivory Coast is expected to start by the end of this year. At Baleine, Brusco confirmed the two vessels to be used at phase two "will be in country in September and, building on the experience of phase one, we expect a couple of months of final integrated commissioning" before first oil. Eni also said today it would raise its dividend for 2024 by 6pc over 2023 to €1/share, and confirmed share repurchases this year of €1.6bn. It said there is potential for an additional buyback of up to €500mn, which is being evaluated this quarter. Eni's debt gearing is scheduled to fall below 20pc by the end of the year. Chief financial officer Francesco Gattei said these accelerated share buybacks would be possible if divestment deals are confirmed. By Jon Mainwaring and Aydin Calik Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Find out more
News

Australia’s Ichthys LNG to restart liquefaction train


26/07/24
News
26/07/24

Australia’s Ichthys LNG to restart liquefaction train

Singapore, 26 July (Argus) — The second liquefaction train at Australia's 9.3mn t/yr Ichthys LNG export terminal plans to resume partial operations today, after going off line unexpectedly during 18-19 July, according to traders. The export facility is operated by Japanese upstream firm Inpex. Repairs at the affected train could take up to a month before it returns to full production, although the train is expected to restart by this weekend, according to market participants. Attempts to restart train two could take place by 26 July. Some delays to deliveries from the facility are expected, although there are also unconfirmed reports that up to two cargoes may have already been cancelled at the time of writing. The overall impact on the market is likely to be limited for now, with continuing weak spot demand from northeast Asian importers. Some term buyers previously requested for their deliveries to be deferred, traders said, although it is unclear just how many requests for deferment were received. But other participants have pointed out that the winter restocking season could soon start and any further impediments to train two's restart could lift prices. Recent temperatures in Japan have been higher than expected, with at least a 70pc probability of above-normal temperatures over the vast majority of the country until 23 August, according to the latest forecast issued by the Japan Meteorological Agency on 25 July. At least one Japanese utility may be considering spot purchases for August, owing to higher-than-expected power consumption because of warmer temperatures. But at least two other Japanese firms could be looking to sell a September and an October cargo each, traders said, which could indicate that the spot market is still sufficiently well-supplied to cope with additional demand from Japanese utilities. The 174,000m³ Grace Freesia departed from Ichthys on 25 July after loading an LNG cargo, according to ship tracking data from Kpler. The export terminal sold a spot cargo for loading over 2-6 June at around high-$9s/mn Btu through a tender that closed on 10 May, but further details are unclear. The US' 17.3mn t/yr Freeport export terminal also faced issues restarting since it was first taken off line on 7 July as a precautionary measure against Hurricane Beryl. The terminal loaded its first cargo on 21 July . All three trains are likely to be back on line as of 26 July, although production at the facility should still be closely monitored, traders said. By Naomi Ong Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Australia’s Empire Energy signs deal to sell gas to NT


26/07/24
News
26/07/24

Australia’s Empire Energy signs deal to sell gas to NT

Adelaide, 26 July (Argus) — Australian independent Empire Energy has signed an agreement to supply the Northern Territory (NT) with gas from its Carpentaria project in the onshore Beetaloo subbasin. Empire will supply NT with up to 25 TJ/d (668,000 m³/d) of gas over 10 years, starting from mid-2025. This equates to an estimated total supply of 75PJ (2bn m3) of gas. The deal includes scope for an additional 10 TJ/d for up to 10 years if production level at the Carpentaria plant exceeds 100 TJ/d. The firm bought domestic utility AGL Energy's dormant 42 TJ/d Rosalind Park gas plant late last yearwith plans to reassemble the facility on site at Carpentaria, subject to a final investment decision on the project. Gas will be delivered to the NT government-owned Power and Water (PWC) via the McArthur River gas pipeline on an ex-field take-or-pay basis, Empire said on 26 July. PWC in April signed an agreement to buy 8.6PJ of gas from Australian independent Central Petroleum , to supply gas-fired power generation and private-sector customers. Low production at Italian energy firm Eni's Blacktip field, offshore the NT, has led PWC to court new supply while providing a new outlet for prospective producers operating within Beetaloo. The largest Beetaloo acreage holder, Tamboran Resources, has revealed ambitious plans for a 6.6mn t/yr LNG plant to be located near Darwin Harbour's two existing LNG projects, using the basin's shale gas resources as feedstock. By Tom Major Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Refining, LNG segments take Total’s profit lower in 2Q


25/07/24
News
25/07/24

Refining, LNG segments take Total’s profit lower in 2Q

London, 25 July (Argus) — TotalEnergies said today that a worsening performance at its downstream Refining & Chemicals business and its Integrated LNG segment led to a 7pc year-on-year decline in profit in the second quarter. Profit of $3.79bn was down from $5.72bn for the January-March quarter and from $4.09bn in the second quarter of 2023. When adjusted for inventory effects and special items, profit was $4.67bn — slightly lower than analysts had been expecting and 6pc down on the immediately preceding quarter. The biggest hit to profits was at the Refining & Chemicals segment, which reported an adjusted operating profit of $639mn for the April-June period, a 36pc fall on the year. Earlier in July, TotalEnergies had flagged lower refining margins in Europe and the Middle East, with its European Refining Margin Marker down by 37pc to $44.9/t compared with the first quarter. This margin decline was partially compensated for by an increase in its refineries' utilisation rate: to 84pc in April-June from 79pc in the first quarter. The company's Integrated LNG business saw a 13pc year on year decline in its adjusted operating profit, to $1.15bn. TotalEnergies cited lower LNG prices and sales, and said its gas trading operation "did not fully benefit in markets characterised by lower volatility than during the first half of 2023." A bright spot was the Exploration & Production business, where adjusted operating profit rose by 14pc on the year to $2.67bn. This was mainly driven by higher oil prices, which were partially offset by lower gas realisations and production. The company's second-quarter production averaged 2.44mn b/d of oil equivalent (boe/d), down by 1pc from 2.46mn boe/d reported for the January-March period and from the 2.47mn boe/d average in the second quarter of 2023. TotalEnergies attributed the quarter-on-quarter decline to a greater level of planned maintenance, particularly in the North Sea. But it said its underlying production — excluding the Canadian oil sands assets it sold last year — was up by 3pc on the year. This was largely thanks to the start up and ramp up of projects including Mero 2 offshore Brazil, Block 10 in Oman, Tommeliten Alpha and Eldfisk North in Norway, Akpo West in Nigeria and Absheron in Azerbaijan. TotalEnergies said production also benefited from its entry into the producing fields Ratawi, in Iraq, and Dorado in the US. The company expects production in a 2.4mn-2.45mn boe/d range in the third quarter, when its Anchor project in the US Gulf of Mexico is expected to start up. The company increased profit at its Integrated Power segment, which contains its renewables and gas-fired power operations. Adjusted operating profit rose by 12pc year-on-year to $502mn and net power production rose by 10pc to 9.1TWh. TotalEnergies' cash flow from operations, excluding working capital, was $7.78bn in April-June — an 8pc fall from a year earlier. The company has maintained its second interim dividend for 2024 at €0.79/share and plans to buy back up to $2bn of its shares in the third quarter, in line with its repurchases in previous quarters. By Jon Mainwaring Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Australia’s Origin to expand Eraring battery project


25/07/24
News
25/07/24

Australia’s Origin to expand Eraring battery project

Sydney, 25 July (Argus) — Australian utility Origin will expand the battery energy storage system (BESS) at the site of its 2,880MW Eraring coal-fired power station in News South Wales (NSW), as part of its strategy to pivot to renewable energy. The A$450mn ($294mn) investment will add 240MW of four-hour duration supply to the 460MW, two-hour BESS already under construction as part of the project's first stage, Origin said on 25 July. Agreements for equipment supply and construction have been made with stage two construction to begin in early 2025 before the expansion comes on line during January-March 2027. Equipment will be provided by Finnish engineering firm Wartsila, which is also building the first stage of the BESS. The sanctioning of Eraring's second stage brings the firm's total commitment on storage to 1.5GW, with Origin agreeing in January to outlay A$400mn on a 300MW BESS along with the firm's 550MW Mortlake gas-fired power plant in Victoria. Origin and the NSW Labor state government agreed in May to keep Eraring, Australia's largest single power plant, open for at least two more years as part of a deal to maintain capacity because of delays with replacement projects. Australia is struggling to replace its retiring coal-fired power generation because of cost blowouts and delays for renewable projects. By Tom Major Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Generic Hero Banner

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more