Latest market news

Indonesian Sumsel 1 coal-fired unit eyes December start

  • Market: Coal, Electricity
  • 18/09/24

The first 300MW unit of the 600MW Sumsel 1 mine-mouth coal-fired power plant in Indonesia's south Sumatra province is scheduled to begin commercial operations in December following several years of delays.

The plant, which is located in Muara Enim regency, is being developed by China Shenhua Energy and Lion Power Energy, which have 75pc and 25pc respective stakes in the project. Once fully operational it is expected to consume around 2-3mn t/yr of coal. Lion will be responsible for sourcing the coal.

The $750mn plant is part of Indonesia's 35GW power generation roadmap developed by the Indonesian government in 2015.

The project was contracted to China Shenhua Energy in 2016. The first unit at the plant was originally scheduled for completion by 2020. But land acquisition delays and the Covid-19 pandemic and resulting restrictions on the movement of people and travel bans delayed construction, Lion said.

Construction work on the plant structure is now in the final stages and operational testing is expected to begin soon. But hitting the operational target date also depends on the completion of a 275kV high-voltage line that will connect the plant to the grid, state-owned utility PLN said. The 80km transmission line will pass through four districts in south Sumatra. The local government is pushing for the acceleration of the voltage line construction and has instructed the sub-district head and local government offices to provide support for the power line construction, PLN said.

Sumsel 1, once fully operational, will operate on a build-own-operate basis with a 25-year power supply contract with PLN, the utility said.


Sharelinkedin-sharetwitter-sharefacebook-shareemail-share

Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

News
17/12/24

Alabama lock to remain closed until spring

Alabama lock to remain closed until spring

Houston, 17 December (Argus) — The US Army Corps of Engineers (Corps) has determined that the main chamber of the Wilson Lock on the Tennessee River near Florence, Alabama, will remain closed until spring 2025 as repairs continue. The Wilson Lock, the first lock on the Tennessee River, closed on 25 September after cracks in the lock gates on both the land and river sides were discovered. The main lock was closed to prevent further damage in the main chamber, although the auxiliary chamber was kept open for navigation. The Corps had been eyeing an earlier opening date for the main chamber since the start of November. Although months of repairs have taken place, the Corps resolved to keep the main chamber closed to preserve the lock and maintain personnel safety. The Corps, in partnership with the Tennessee Valley Authority (TVA), is still assessing the root cause of the cracking. A second de-watering of the gate is scheduled for the first three months of 2025 to repairs. No official date has been set for the lock reopening, although some barge carriers have heard of a late April opening date. A regular 15 barge tow has endured 5-6 days of delay through the lock on average, according to carriers. The Corps' Lock Status Report on the Wilson Lock reported a nearly two-week delay for tows navigating through the lock. This has been costly for shippers by forcing them to pay delay fees. Wilson Lock is the second lock in Alabama to undergo a lengthy closure this year. Most lock and dams along the US river system are over 70 years old, likely resulting in more closures in the coming year. By Meghan Yoyotte Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Find out more
News

US river lock closures may delay product deliveries


13/12/24
News
13/12/24

US river lock closures may delay product deliveries

Houston, 13 December (Argus) — Mid-Mississippi River and Illinois River locks are expected to undergo long-term closures starting next month, slowing down some commodity deliveries. Three locks around the St Louis, Missouri, and Granite City, Illinois, region will be closed for repairs for up to three months starting 1 January, according to the US Army Corps of Engineers. The Mel Price Main Lock, where the Illinois River flows into the Mississippi River, and Lock 27's main lock, where the Missouri flows into the Mississippi, will also be closed from 1 January through 1 April. The Mel Price Main Lock will commence the final phase of replacement for its upstream lift-gate. Replacement of embedded metals will occur during the closure for Lock 27's main lock. Lock 25 will have a shorter closure date for a sill beam and guide-wall concrete installment from 1 January through 2 March. This is the first lock on the upper Mississippi River, after the Illinois River. These closures are expected to be more of a nuisance than a deterrent for commodity traffic, according to barge carriers. Ice in the river is likely to have melted by mid-March, which may cause barge carriers to wait in the St Louis harbor for the locks to open. Two other lengthy closures are anticipated on the Illinois River beginning on 28 January. The Lockport Lock — the second to last lock on the Illinois River — will be fully closed from 28 January through 25 March for full repairs to the sill and seal of the lock. The prior lock, Brandon Road Lock, will be closed during weekdays over the same time period, but traffic can pass through over the weekend. The lock closures and repairs are expected to delay some barge shipments, specifically to the Great Lakes and Burns Harbor. By Meghan Yoyotte Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Argentina’s renewables to get boost in 2025


13/12/24
News
13/12/24

Argentina’s renewables to get boost in 2025

New York, 13 December (Argus) — Argentina's renewables sector is looking at a rosier outlook in 2025 supported by new legislation and improved economic conditions. The country's renewable energy legislation, which was enacted in 2015 and expires at the end of 2025, stipulates a target of 20pc participation of renewables — excluding hydropower plants greater than 50MW — by the end of 2025. The country has not met annual targets, but there is growing confidence that it could come close to the goal by the end of next year. Renewable sources covered 15pc of the demand in October, according to the latest report from the energy secretariat, up from 13.5pc in July. The country added 373MW in new renewable generating capacity in the first three quarters of this year. The trade organization of wind energy CEA, estimates that 700MW in new solar and wind capacity will be added in 2025. A replacement renewable law focused primarily on investment, which the ruling Libertad Avanza party plans to submit in early 2025, and economic deregulation underway has the sector confident that financing for projects will soon be readily available, ushering in a boost in private investment for renewables. Ignacio Criado, a partner at the Tanoira Cassagne law firm who focuses on renewable energy, said he expects the country to be close to the 20pc renewable target by the end of 2025 and that there will be sustained growth in coming years. "More players are interested in the construction of renewable energy plants, with solar power in the north and wind in the south," said Criado. He said that the country's increasing economic stability and a government program providing incentives for large-scale investments, known as the RIGI, are fostering interest among investors. Argentina's economy, while still in tough shape, has improved in the year since president Javier Milei took office. While annualized inflation is still in triple digits, the monthly rate fell from 25.5pc in December 2023 to 2.4pc in November, according to the statistics agency. It was 112pc in the 12 months through November. The economy shrank by 3.4pc in the first half of the year and will contract by around 3pc the full year, but is expected to grow by 5pc in 2025, according to the IMF. During a 10 December address marking his first year in office, Milei said tax reform and elimination of exchange rate and customs controls would be forthcoming, adding to investment flows. RIGI boost The administration has already received requests under the RIGI mechanism for $11.8bn in investment, primarily in energy projects, Milei said. Among the projects in line for the RIGI is the state-owned YPF Luz's 305MW El Quemado solar plant, the first stage of which should be ready by 2026. In early December, the state's energy wholesaler, Cammesa, awarded a contract for eight new renewable projects with a combined capacity of 561MW. It received 31 proposals for a total of 1,639MW. Of the projects, 345MW were awarded to Genneia, the country's largest renewable company with more than 1GW in installed capacity, and 88MW to Australia's Fortescue for its Cerro Policia wind farm in the southern Rio Negro province. The energy will be used for its planned low-carbon hydrogen project. These projects should start coming on line from the end of 2025 in throughout 2026. As of October, Argentina had 6.56GW in installed renewable capacity, including 4.12GW in wind, up by 11.2pc from a year ago, 1.63GW in solar, up by 19.6pc, and 82MW in biogas, up by 5.4pc. It also had 524MW in small hydroelectric plants and 201MW in biomass, with no new capacity from a year earlier. Large-scale hydroelectric plants totalled 9.63GW, while thermal electric plants totalled 25.28GW and nuclear plants 1.75GW. By Lucien Chauvin Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Norway's 500MW cables at risk if price link proved


13/12/24
News
13/12/24

Norway's 500MW cables at risk if price link proved

London, 13 December (Argus) — Norway will not replace the two oldest transmission cables between it and Denmark, with a combined capacity of 500MW, if the national transmission system operator (TSO) confirms they "harm the national power system", energy minister Terje Aasland told Argus . If the Skagerrak 1 and 2 cables are found to contribute to "high prices", as seen this week, and additionally "reinforced negative price contagion", the minister explained, the government will not renew the cables. The minister's comments come as the ruling Labour party's programme committee — of which the minister is not a member — agreed to block extending or replacing the ageing cables as they approach the end of their operational lifetime. There has yet been no formal application to renew the Norwegian-Danish Skagerrak 1 and 2 links, which the minister said means "there is nothing to say yes or no to" at the moment. Norwegian TSO Statnett is currently investigating the possible renewal and, alternatively, the effects of not renewing the link, the minister confirmed. Skagerrak 1 and 2, commissioned in 1976 and 1977, respectively, are part of a trio of cables, including the 500MW Skagerrak 3 interconnector connected in 1993, linking Norway's NO2 with Denmark's DK1 bidding area. By Daniel Craig Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

New Zealand boosts coal-fired generation in Jul-Sep


13/12/24
News
13/12/24

New Zealand boosts coal-fired generation in Jul-Sep

Sydney, 13 December (Argus) — New Zealand's power providers ramped up coal-fired generation during the July-September quarter, according to data from the Ministry of Business Innovation and Employment (MBIE), because of weaker hydroelectric generation. New Zealand's energy producers generated more coal-fired power between July-September compared to the same period of last year as hydropower storage levels slid across the country to a low of approximately 1,600GWh in August. Producers generated 884GWh of coal-fired power during the quarter, more than doubling on the year. This accounted for 8pc of the country's electricity generation during the quarter. In comparison, coal accounted for 3pc of the power mix in the same quarter a year earlier. The country's electricity authority in July reported that New Zealand's coal stockpile was relatively low at 140,000t, but producers had used 363,513t to generate electricity by September, indicating that imports were supporting the increased demand. New Zealand's coal imports increased by more than fourfold on the year in July-September, with importers shipping over 477,379t of sub-bituminous coal into the country, according to data from the MBIE. In comparison, the country imported 240,305t of coal over the whole of 2023. Some power providers started preparing to increase their use of coal generators early this year. New Zealand's largest utility Genesis Energy in May announced it plans to import coal into the country for the first time since 2022 , following a drop in gas and hydroelectric production. Major utility Meridian Energy reported in October that water levels at the Lake Pūkaki – New Zealand's largest hydroelectric storage lake – hovered below 91-year averages between May-August. But "all the rain [Lake Pūkaki] missed from April to August finally arrived in September," the company's general manager of wholesale, Chris Ewers, said. New Zealand's state-owned transmission provider, Transpower, has recorded increases in hydropower storage levels since late August, limiting the need for further coal generation. Storage levels in both the North Island and South Island currently exceed January levels. The country's appetite for coal has grown alongside a loosening of fossil fuel restrictions. New Zealand's current government decided to weaken coal mine consenting rules during its first round of planning reforms in late 2023, in an attempt to boost production. The government amended the Resource Management Act to allow miners to construct coal mines that affect wetlands, when previously mines affecting wetlands were banned. Resources minister Shane Jones in June introduced legislation to restart offshore oil and gas exploration across the country, reversing the previous government's ban. "Natural gas is critical to keeping our lights on… especially during peak electricity demand and when generation [from intermittent sources] dips," he said. By Avinash Govind Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Generic Hero Banner

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more