Q&A: If you break it down, it is tried, tested: Xlinks

  • Market: Electricity
  • 18/11/24

Project developer Xlinks plans to connect 11.5GW of Moroccan wind and solar capacity, and a 5GW battery energy storage system, with the UK through two 1.8GW sub-sea cables, an ambitious project using "tried and tested" technologies. Argus spoke to chief executive James Humfrey about the project's timeline and progress. Edited highlights follow:

For those who may not know, can you describe the Xlinks project?

We are excited to bring clean energy from the Moroccan Sahara to north Devon. This will be a transformational surge of reliable, clean power, and we will bring it during the hours the UK needs electricity most, supporting Britain's ambitions to decarbonise, which you see in the news and most recently in Baku [at Cop 29].

The project will benefit the broader economy by displacing expensive, volatile imported gas and reducing wholesale power prices. It will also help balance the grid, feeding into the south of England, which has very high demand without significant grid upgrades. The independent Afry consultancy group calculated the project's socioeconomic benefit to be £17bn.

It will also offer a reliable wind and solar energy supply, with nearly two times the solar radiation factor. [Moroccan] wind generation is slightly negatively correlated to UK output, helping overcome the dunkelflaute [dark lull] scenario, which is the advantage of moving electrons in time and space. This reliability complements the UK domestic renewables pipeline, primarily offshore and onshore wind, while aligning with Morocco's green export ambitions.

Can you provide our subscribers with an update on the project, its timeline and any key milestones?

It will be ready next decade. And we are set up to rapidly mobilise and deliver the project. We have a strong team of people who have worked on these projects before. For example, our HVDC cable team, led by Nigel Williams, built the North Sea Link between Blythe and Norway, tackling more complex problems than we face. They've built lots of interconnectors and know how to do it.

I realise that Xlinks holds connection agreements for two 1.8GW connections with National Grid. Has Xlinks progressed with other national authorities, particularly those through which the cable will transit?

We have worked with the Moroccan government, including [plans] around the land and conducting one of the world's longest [wind and solar] measurement campaigns. So, we've got excellent resource data regarding wind and solar energy.

We have already obtained permits from [the transit countries] for route surveys and we have vessels in the water at the moment, undertaking geophys and geotech. Next year, we'll apply for the final installation permits, based on the environmental studies and other benefit data.

We've taken a longer but less challenging route, with lower water depths, making it technically easier. It is, for example, less deep than the North Sea Link, which was a deliberate technical decision.

The previous government marked Xlinks as a project of national significance. Do you expect any change under the new administration, and in what way has this classification affected progress?

No, it hasn't affected us. We completed the public consultations over the summer and are about to submit our DCO [development consent order] application, which is a large amount of work. We have finished that, with no changes [since the change of government]. It is probably worth saying that our land route in Devon is all underground. We don't have any pylons, which is much less intrusive.

Has this improved Xlink's ability to generate capital interest? Is there any specific attempt to generate interest from sovereign wealth funds or other institutional investors?

We've been fortunate that our blue-chip investors [Octopus, TotalEnergies, Taqa, GE Vernova and Africa Finance] are very keen on the project, and it matches their strategic plans. They want to go all the way through to construction. We may have further investors at the close, but they are our primary focus right now.

Do you have an update on the contract for difference (CfD) process? Xlinks has published a desire to reach a £70-80/MWh strike price at 2012 prices.

Yes, that remains our guidance. We are working through the CfD and Treasury Green Book process with the Department of Energy. It is quite a structured process.

How do you reconcile that strike price with far lower prices reached in recent allocation rounds (AR), namely AR6, although the technologies are not directly comparable?

Firstly, in the NESO report, the forecasts for offshore wind [prices] rise quite a bit as they move out to 2030, so AR6 is a reference, but there are figures in the NESO report that are above our £70-80 [strike price]. Importantly, it is not a comparison between apples and apples. Our profile is completely different from that of offshore wind.

We offer firm power for 19 hours a day, optimised for peak hour demand and very high reliability, akin to nuclear. Given our flexibility, we can also provide various other services, including frequency and even black start services.

The development contains ambitious plans for vast-scale battery storage of up to 5GW. Given the difficulties faced by several European battery manufacturers, do you foresee any significant supply chain challenges?

We have an ongoing battery procurement process, and the invitations to tender have gone out. We've had good interest at competitive levels and are confident in it. We are not seeing any challenges, and it's going very well.

And what does the flexibility and opportunity a battery offers at this scale mean for a project like Xlinks?

It allows us to optimise during the dinural shift of solar power, when the UK grid needs us most. Additionally, it gives us a sub-second response, giving us flexibility and opening the door to the frequency services we mentioned earlier. It is very valuable and allows us to provide benefit at scale and at speed.

Does the UK's ambition, corroborated by NESO's latest report to become a net power exporter beyond 2030, change the project's economic viability or impact it in any way?

No, the report does not change our viability or where we fit in the future system. In fact, it further emphasises the part we can play. If you look at demand, it is very likely to increase again by another 23pc in 2030-35, and considering our generation profile, producing in periods of low domestic wind production, [it fits well]. Additionally, when we compare it to other sources of clean [baseload] generation, such as nuclear, you see solar, wind and transmission projects have extremely good predictability of outcome and a shorter delivery timeline.

Xlinks has stated an ambition to investigate a Morocco-German link. What might this look like? Would it involve an entirely new generation facility, too?

First, the Morocco-UK power project is very much our first priority. We're focused on that and we think bringing this to a financial close will help unlock a range of projects across the industry. And demonstrate the art of the possible. We do have some early feasibility work going on. It would be entirely separate, and that would include generation as well.

Do you have any closing thoughts that you would like to leave our subscribers?

What is different about this is its scale. But when you break it down, these are all tried-and-tested technologies. There is nothing unusual about them, whether wind and solar in Morocco or large-scale batteries. We are not an interconnector, but long-distance transmission has a long history in the UK. When you look at the water depths, it is less complicated than North Sea Link. It has all been done before, in its parts — just the scale is different.


Sharelinkedin-sharetwitter-sharefacebook-shareemail-share

Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

News
30/04/25

Brazil's energy transition spending drops in 2024

Brazil's energy transition spending drops in 2024

Sao Paulo, 30 April (Argus) — Brazil's mines and energy ministry's (MME) energy transition spending shrank by 83pc in 2024 from the prior year, while resources for fossil fuel incentives remained unchanged, according to the institute of socioeconomic studies Inesc. The MME's energy transition budget was R141,413 ($24,980) in 2024, down from R835,237 in the year prior. MME had only two energy transition-oriented projects under its umbrella last year: biofuels industry studies and renewable power incentives, which represented a combined 0.002pc of its total R7bn budget. Still, despite available resources, MME did not approve any projects for renewable power incentives. It also only used 50pc of its budget for biofuel studies, Inesc said. Even as supply from non-conventional power sources advances , most spending in Brazil's grid revamp — including enhancements to better integrate solar and wind generation — comes from charges paid by consumers through power tariffs, Inesc said. Diverging energy spending Brazil's federal government also cut its energy transition budget for 2025 by 17pc from last year and created a new energy transition program that also pushes for increased fossil fuel usage. The country's energy transition budget for 2025 is R3.64bn, down from R4.44bn in 2024. The new program — also under MME's umbrella — has a budget of around R10mn, with more than half of it destined to studies related to the oil and natural gas industry, Inesc said. A second MME program — which invests in studies in the oil, natural gas, products and biofuels sectors — has an approved budget of R53.1mn. The science and technology ministry is the only in Brazil that increased its energy transition spending for 2025, with R3.03bn approved, a near threefold hike from R800mn in 2024. Spending will focus on the domestic industry sector's energy transition, Inesc said. Despite hosting the UN Cop 30 summit in November, Brazil has constantly neglected to address the phase-out of fossil fuels, drawing the ire of climate activists . By Maria Frazatto Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

Find out more
News

Nemos commit to 15-minute settlement in power SDAC


30/04/25
News
30/04/25

Nemos commit to 15-minute settlement in power SDAC

London, 30 April (Argus) — Eleven nominated electricity market operators (Nemos) have confirmed their "readiness and commitment" to proceed with a 15-minute settlement in the single day-ahead coupling (SDAC) market on 11 June, according to a statement given to Argus . The co-signing Nemos — Oslo-based Nord Pool, Czech OTE, Austrian EXAA, Greek Enex, Italy's GME, Spain's Omie, Bulgarian Ibex, Poland's TGE, Slovakian Okte, Croatia's Cropex and Romanian BRM — confirmed that they "do not share the misgivings" about the 15-minute settlement transition expressed by European power exchange Epex Spot earlier this month , the Nemos told Argus . Nord Pool previously told Argus on 17 April that it was "confident and ready" to deliver 15-minute trading. The market operators do "not recognise" the problems cited by Epex and are sure that the "necessary infrastructure and processes" are in place to implement the move on time successfully. Instead, the co-signed Nemos stressed that the transition is a "pivotal advancement" and any delay risks "hinder[ing] progress" towards a better-integrated market. Specifically, the signatories clarified that the decoupling registered in some tests and cited by Epex Spot was not "due to a lack of reliability" in the system. Instead, they attributed this to "internal local testing issues of certain parties in the initial [testing] stage". The Nemos added that all performance tests of the central matching algorithm (Euphemia) were "successfully completed and validated by all parties, including Epex Spot". The co-signed Nemos noted that most test scenarios, "both functional and procedural", were "successfully completed and validated", adding that any reference to the implicit intraday auction (IDA) decoupling scenario is "misleading and inappropriate" as these were "caused by local issues" and the "time allocated to IDA executions" is less than 25pc of the "overall time available for SDAC". By Daniel Craig Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

News

France to review role of renewables in energy plan


30/04/25
News
30/04/25

France to review role of renewables in energy plan

London, 30 April (Argus) — The French government will delay the publication of its 10-year energy plan (PPE), and could change its content to take into account criticism that it gives too much priority to renewables, after a debate in the French parliament earlier this week. Prime minister Francois Bayrou on 28 April held a parliamentary debate on the much-delayed plan, which was initially due to come out in 2023. Publication appeared imminent last month, but revolts in the parliament — in which the prime minister does not have a majority — have forced the government to reconsider. The government will take its decisions "in some months", Bayrou told the parliament. "This PPE is not written in advance and everyone will be able to contribute before the final version," he said, opening the door to a rewrite of the plan, which committed to large increases in wind and solar photovoltaic capacity. A commission will deliver a report at the end of May, to be followed by a parliamentary debate on a version of the plan authored by senator Daniel Gremillet in June. The government's support for renewable energy will be "reasoned", he said, suggesting there could be a scaling back of wind and solar ambition. Bayrou highlighted the problems of solar energy, including that its peak output does not correspond to peak demand periods. To solve this problem, France must make its demand more flexible — including through the upcoming reform of tariffs, which will offer lower prices to some customers in the middle of the day — and through developing storage, he said. But the question of cost remains. Roof-mounted installations in France — the sector which has advanced the fastest over the past year — produce at a cost of €100/MWh, he said, compared with €40/MWh at large ground-mounted plants in Spain. But the public acceptability of covering large areas of countryside with low-cost solar farms remains a question, he said. And the development of onshore wind must be "reasonable", as public acceptability of the technology diminishes as the number of installations increase, Bayrou said. France must focus on repowering existing sites, he added. And the government firmly supports extending the lifespan of existing nuclear plants, and building at least six more reactors to enter service from 2038, Bayrou said. Right-wing Rassemblement National (RN) called for an increase in nuclear ambition, demanding the construction of 10GW of new nuclear by 2035, upratings at existing reactors and increasing the load factor of the fleet to 80pc. This would put France on the road to increasing its energy mix to 60pc low carbon by then, up from 37pc now, RN deputy Maxime Amblard said. But this would be accompanied by a moratorium on intermittent renewables, especially on wind farms, he said. The centre-left socialists called for the publication of the PPE as is, while left-wing LFI and green parties criticised what they characterised as a lack of ambition on emissions reduction and too heavy a reliance on nuclear. By Rhys Talbot Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

News

Norway's Equinor sees minor fall in 1Q output, profit


30/04/25
News
30/04/25

Norway's Equinor sees minor fall in 1Q output, profit

London, 30 April (Argus) — Norwegian state-controlled Equinor posted a profit of $2.63bn in the first quarter — a decline of 2pc on the year — as production dropped slightly and it reported lower liquids prices. Although its profit fell compared with a "strong" first quarter of 2024, it was an increase of nearly a one third from the fourth quarter of 2024. Equinor's production was 2.12mn b/d of oil equivalent (boe/d) in the January-March period, lower on the year by 2pc. "The production decrease was similar for both gas and liquids," the company said. It cited "strong" operational performance for most of its Norwegian fields, which it said "almost offsets the negative production impact from the shut-in at Sleipner B… and planned and unplanned maintenance at Hammerfest LNG." The Sleipner B platform was shut down in October after a fire . Equinor's US production rose on the year, while its output from international assets fell over the same timeframe owing to its exits from Nigeria and Azerbaijan in 2024. Equinor reported an average liquids price of $70.6/bl in the January-March quarter, down by 7pc on the year. Its realised piped gas prices rose considerably over the same time, to $14.80/mn Btu for Europe and $4.06/mn Btu for the US — increases of 57pc and 74pc, respectively. The company's total first-quarter power generation increased by 9pc on the year, to 1.4TWh, driven by "stronger clean spark spreads in gas to power generation and onshore assets in Brazil." But the renewables share of this slid by 2pc over the same period, to 760,000GWh because of "unfavourable wind conditions." Equinor is considering its legal options with regards to its US Empire Wind project, chief executive Anders Opedal said today. The US government in April ordered work to stop on the planned 810MW wind farm, offshore New York. "We have invested in Empire Wind after obtaining all necessary approvals, and the order to halt work now is unprecedented and in our view unlawful," Odepal said. "This is a question of the rights and obligations granted under legally issued permits, and security of investments based on valid approvals." The company reported a marginal decline in its upstream CO2 intensity in the first quarter 6.1kg CO2/bl, compared with 6.2kg CO2/bl for full-year 2024. There was a similar drop in absolute scope 1 and 2 greenhouse gas (GHG) emissions — at 2.7mn t/CO2 equivalent (CO2e) for the first quarter, compared with 2.9mn t/CO2e a year earlier. Equinor confirmed a cash dividend of $0.37/share for the first quarter and plans to launch a second tranche of its share buyback programme of up to $1.265bn, subject to authorisation at its annual general meeting in May. The first tranche of this year's buyback programme was completed on 24 March with a total value of $1.2bn. By Georgia Gratton Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

News

Indonesia secures $60mn JETP funding for solar power


30/04/25
News
30/04/25

Indonesia secures $60mn JETP funding for solar power

Singapore, 30 April (Argus) — State-owned PLN Indonesia Power (PLN IP) and Saudi-listed Acwa Power will receive $60mn in funding from the Just Energy Transition Partnership (JETP) to develop a solar project in Indonesia, indicating there is still interest in financing the country's energy transition. The 92MW peak (MWp) Saguling floating solar project in west Java will receive the funds from German development finance institution DEG, French development finance institution Proparco and Standard Chartered bank, announced the Glasgow Financial Alliance for Net Zero (GFANZ) on 29 April. PLN IP and Acwa Power signed a power purchase agreement in August 2024 to jointly develop the solar project. The $60mn for the project is in addition to $1.2bn which Indonesia has already secured under the JETP. Indonesia joined the JETP in 2022 and is supposed to receive $20bn through the scheme from international partners including GFANZ, to help its coal phase-out. US president Donald Trump's decision to withdraw the US from the JETP raised concerns earlier in 2025 on whether Indonesia could stick to its energy transition policies. But the US' withdrawal may not necessarily have a major impact on JETP funding. The latest investment "points to appetite from both public and private sectors to finance the country's green energy transition," said GFANZ. France has already mobilised over €450mn ($511mn) for Indonesia's energy transition through the JETP, according to the ambassador of France to Indonesia, Fabien Penone. PLN IP, a sub-holding of state-owned electricity company PLN Persero, is the largest power generation company in southeast Asia. Indonesia's electricity demand is expected to grow by about 3.8pc/yr to 1,813TWh/yr by 2060, but its power sector is still heavily reliant on coal, which made up 61.8pc of the electricity mix in 2023. In comparison, renewables made up 19pc, out of which solar and wind power constituted a mere 0.2pc. Indonesia has large solar potential of up to 3,295GW, said PLN IP's president director Edwin Nugraha Putra. The Saguling solar project, which is expected to reduce carbon emissions in Indonesia's power system by at least 63,100 t/yr, will also increase the share of solar in Indonesia's electricity production by around 13pc, according to GFANZ. The share of renewables in Indonesia's power mix is expected to rise to around 21pc by 2030 and 41pc by 2040, according to think-tank Ember. By Prethika Nair Send comments and request more information at feedback@argusmedia.com Copyright © 2025. Argus Media group . All rights reserved.

Generic Hero Banner

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more