Cyprus strives to keep control of Aphrodite field

  • Market: Natural gas
  • 11/10/23

The government and Chevron have extended their negotiations to chart a course forward for the field, write Nader Itayim and Antonio Peciccia

Progress is being made on a revised development plan for Cyprus' 118bn m³ Aphrodite gas field, after the Cypriot government rejected a previous version of the plan that would have essentially handed control of the field to Egypt, energy minister George Papanastasiou tells Argus.

There has been "some progress" during talks between the government and Aphrodite's operator, Chevron, over the field's development and production plan, Papanastasiou said on the sidelines of the Adipec conference in Abu Dhabi earlier this month. In light of the progress made, the parties have pushed back the original timeline for the negotiations by 30 days, and they are now scheduled to be concluded by 5 November, Papanastasiou says, adding that he is "optimistic" about the outcome. Alongside Chevron, the field's shareholders include Shell and Israeli firm NewMed Energy.

According to Papanastasiou, at the core of the negotiations is Chevron's decision to remove from the plan a floating production unit (FPU) that was meant to be built within the area of the reservoir. Instead, Chevron proposed connecting Aphrodite through a sub-sea pipeline to an existing processing and production facility in Egypt — although not the Idku liquefaction terminal, as the 2019 plan specified. Removing the FPU from the plan means control of the field "is no longer in Cyprus or the exclusive zone", Papanastasiou says. "It's in Egypt."

Cyprus and Egypt have been working on a plan to link the Aphrodite field to Egypt's existing liquefaction facilities for several years. But negotiations had stumbled on the issue of resource allocation between the Egyptian domestic market and LNG exports, stemming from concerns that Egypt might prioritise the domestic market over LNG exports — as it did in the wake of the 2011 revolution, eventually leading to the country halting exports altogether and turning into an LNG importer for much of last decade. The issue may have become an even stickier point in recent years as Egypt's supply surplus for exports has been shrinking, and the country is able to export LNG only during periods of lower domestic demand in the winter.

But reverting — at least partially — to the 2019 development plan also poses challenges, particularly related to the area's lack of infrastructure and the difficulty in underpinning the necessary investments. Papanastasiou describes the absence of infrastructure as "the fundamental difficulty". "I don't know how they plan to manage that one," he admits.

Building the necessary infrastructure is "the most important thing" for Cyprus, not just because of Aphrodite but also to serve a number of more recent discoveries in the country's exclusive economic zone (EEZ). These finds — the Cronos, Calypso, Zeus and Glafcos fields, which Papanastasiou calls the "southwest cluster" — have also made little progress. To bring all these reserves to the market, one option is to tie them to infrastructure already in the area, in Egypt or Israel. The other option is to build separate infrastructure, but "you have to justify that investment, and this is the difficulty we are facing at the moment", Papanastasiou says. All of these fields have yet to submit formal development plans, although Italian energy firm Eni is considering linking Cronos to a tie-back to Egypt, he says.

Regional co-operation

The infrastructure issue highlighted by Papanastasiou betrays a lack of clarity on the target market for the Cyprus discoveries.

The option to link the fields to infrastructure in Egypt would benefit from its large domestic market, as well as existing liquefaction facilities. Instead, the alternative mooted by Papanastasiou is to co-operate on infrastructure development with Israel, which is looking for "an alternative export route other than Egypt" for its offshore gas resources, Papanastasiou says. Israel only exports gas by pipeline to Egypt and Jordan at present, although it has been considering plans to install a floating liquefaction unit that would give it access to the international LNG market.

Nicosia has made a proposal that includes a pipeline to connect Cyprus with Israel's gas grid, the minister says. This would enable Cyprus to import Israeli gas for use in power generation.

But investing in such a project would not be justified if the plan targeted only Cyprus' small and undeveloped domestic market. "You need an export side of this arrangement in order to get some LNG", which would require the construction of either a floating liquefaction unit or a modular LNG export plant that could be expanded as more gas becomes available, the minister says. But "at the end of the day, you need an owner of gas", a company that could be the investor and owner of gas at the same time, Papanastasiou says, adding that this could be "any player in the EEZ of Israel or Cyprus".

Still awaiting first gas

The island currently has no access to natural gas supplies and relies almost entirely on fuel oil and diesel for power generation, at least until a planned LNG import terminal in Vasilikos is commissioned next year.

The terminal, which will use the 136,600m³ Etyfa Prometheas as a floating storage and regasification unit (FSRU), is expected to be commissioned in July 2024 and deliver first gas in July-August, Papanastasiou says. This goal is slightly later than the energy ministry's previous target of commissioning in the first half of next year. The project started construction in September 2020 and has already suffered numerous delays.

Papanastasiou suggested that the FSRU, which is expected to be delivered this month, could "be time-chartered to another member state… until the terminal in Vasilikos is completed". Abu Dhabi's state-controlled Adnoc has expressed interest in sub-chartering the vessel.

The project is part of Cyprus' wider push to revamp its electricity system in order to reduce power prices. The terminal would aid conventional power generation by feeding the adjacent 868MW Vasilikos plant. Two more independent power producers are expected to "come into play at about the same time [as Vasilikos]", Papanastasiou says.

And the government plans to upgrade the electricity grid and invest in power storage to help the country cope with a surplus of renewable generation in shoulder seasons, the minister says. At present, the country produces more from renewables than the grid can handle, and the plants do not have batteries in which to store power, Papanastasiou says. In autumn and in spring, when power demand is lower because of reduced cooling and heating needs, "there will be a rejection of renewable energy, which is not right". Additionally, in conventional power generation, "there is a minimum production — 250MW — that you cannot go below", he says.

Cyprus aims to boost the share of renewables in its generation mix to 40pc by 2030, from close to 32pc at present, Papanastasiou says, emphasising that this will only heighten the need for grid improvements to handle the increase in renewables. The government is holding a public consultation on its plans to build power storage capacity and is considering whether to invest directly in the plan. "We expect some interest from the private sector in order to install some systems, but we are also considering doing something that is state owned, because this will be far quicker," he says.


Sharelinkedin-sharetwitter-sharefacebook-shareemail-share

Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

News
28/11/24

Japan’s Saibu Gas to launch terminal expansion in 2029

Japan’s Saibu Gas to launch terminal expansion in 2029

Singapore, 28 November (Argus) — Japanese gas retailer Saibu Gas expects to start commercial operations at its Hibiki terminal expansion between the second and third quarter of 2029. The firm has reached a final investment decision (FID) for the Hibiki terminal expansion, the firm said on 28 November. Saibu's expansion plan includes building a third LNG storage tank with a capacity of 230,000m³, as well as gas production and LNG tank truck-loading facilities. The total project cost is estimated to be around ¥50bn ($330m), and construction will start around summer 2025. The firm issued the tender for expansion in March. This is part of the firm's efforts to meet domestic gas demand "for carbon neutrality", Saibu said. It is also considering introducing e-methane in the future to further enhance its decarbonisation efforts. Saibu Gas plans to expand its global business by utilising the Hibiki terminal to reload cargoes to sell to overseas customers using isotank containers . The terminal has two existing 180,000m³ tanks and sits at Kita-Kyushu in west Japan's Fukuoka prefecture. It is jointly operated by Kyushu Electric and Saibu Gas. The terminal will supply regasified LNG through pipelines to the new 620MW Hibiki LNG-fired power plant at Hibikinada, in the southern Fukuoka prefecture. The facility is expected to start commercial operations in 2026 and it is operated by Hibiki Power, a joint venture between Kyushu (80pc) and Sabu (20pc). By Naomi Ong Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Find out more
News

Japan’s Kline receives new LNG-fuelled car carrier


28/11/24
News
28/11/24

Japan’s Kline receives new LNG-fuelled car carrier

Tokyo, 28 November (Argus) — Japanese shipping company Kawasaki Kisen Kaisha (Kline) received an LNG-fuelled car carrier on 28 November, as it looks to use more lower-carbon marine fuels as part of its decarbonisation efforts. Kline received the car carrier Pontus Highway with a capacity of 7,000 vehicles from Chinese shipbuilder China Merchants Jinling Shipyard. The vessel is equipped with a dual fuel engine and is designed to curb emissions of CO2 by 25-30pc, sulphide oxide by almost 100pc and nitrogen oxide by around 75pc, compared to conventional fuel oil. Kline previously commissioned the LNG-fuelled car carrier Nereus Highway , also built by China Merchants Jinling Shipyard, in the first half of August . It received LNG-fuelled car carrier Poseidon Highway , built by domestic shipbuilder Imabari Shipbuilding, on 1 October . Kline said LNG-fuelled ships have an advantage in securing fuel as supply facilities for these vessels are well-established at ports, especially compared to methanol- and ammonia-fuelled vessels. By Nanami Oki Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Australia’s Santos wins costs in gas pipeline case


28/11/24
News
28/11/24

Australia’s Santos wins costs in gas pipeline case

Townsville, 28 November (Argus) — Australian independent Santos will receive millions of dollars in legal costs, months after the Federal Court ruled in the firm's favour regarding a lawsuit intended to derail its $4.6bn Barossa gas field in the Timor Sea. Environmental law group the Environmental Defenders Office (EDO) must pay Santos' legal bills of slightly more than A$9mn ($5.8mn), 100pc of the company's costs incurred defending a 2023 court case. The EDO's lawyers claimed Barossa's gas export pipeline required a new environmental plan because of cultural heritage matters, but the court found the action brought on behalf of three Tiwi islander Aboriginal people failed to establish any new facts following a cultural survey along the route of the 262km pipeline. Justice Natalie Charlesworth dismissed the independence and credibility of an EDO-commissioned underwater map showing cultural sites, with court papers released showing an expert offered to move the location of one such site so it would conflict with the pipeline. The decision may have a chilling effect on further legal challenges to oil, gas and coal projects in Australia. Court action planned against Australian independent Woodside's $12.5bn Scarborough project offshore Western Australia was called off in August , with the applicant labelling the case as "expensive and risky". Australia's conservative Coalition alliance has promised to end taxpayer funding for the EDO if it wins control of federal parliament in 2025. The October 2022 budget pledged A$9.8mn over four years and A$2.6mn/yr in ongoing funding to the EDO and fellow national legal organisation Environmental Justice Australia. Santos plans to bring its $4.6bn, 84pc complete Barossa field in the Timor Sea on line in July-September 2025, a slight delay from the previously guided first half of 2025. The field will provide feedstock for the 3.7mn t/yr Darwin LNG terminal, which exported its final cargo from the Bayu-Undan field in 2023. By Tom Major Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

LNG use poses risk to Cambodia's energy security: IEEFA


28/11/24
News
28/11/24

LNG use poses risk to Cambodia's energy security: IEEFA

Singapore, 28 November (Argus) — Cambodia's increasing reliance on LNG for power generation could be detrimental to its energy security because of instability in LNG markets, according to Institute for Energy Economics and Financial Analysis (IEEFA). Rapid economic growth and electrification have led to Cambodia's electricity demand growing by 16pc/yr since 2009, according to IEEFA's report released on 26 November. Its power generation is mostly from hydropower and coal, but the country aims to boost its gas-fired power generation to meet its decarbonisation targets. Cambodia has a net zero by 2050 goal, and aims to reach 70pc renewable energy generation by 2030. The share of coal in Cambodia's power mix was 45pc in 2023, with hydropower representing 44pc, solar 5pc and imports from neighbouring countries making up the remaining 6pc. The country in 2021 declared that it would not build new coal plants beyond those already approved. Natural gas had not played a role in the country's power mix until recently, but "optimism has grown in recent years regarding the ability of new LNG-to-power projects to help the country meet rising electricity demand," stated the report. Gas operator Cambodian Natural Gas imported the country's first LNG shipment in 2020 from China's state-owned firm CNOOC, according to IEEFA. The firm also planned to complete a 1,200MW LNG-fired power plant and a 3mn t/yr import terminal by 2023, although there has been no progress as of June this year. Cambodian officials in November 2023 announced the cancellation of a 700MW coal project, which will be replaced with a 800MW gas-fired power plant instead. Cambodia is seeking to build these large LNG-fired power plants because of concerns over the intermittency of renewables such as wind and power, and LNG is viewed as a suitable transition fuel for grid reliability. The government expects LNG-fired capacity to reach 900MW by 2040, which would require roughly 840,000 t/yr of imports. When considering long-term wholesale prices of $8-16/mn Btu, Cambodia's LNG import bill could range between $361mn-722mn/yr, according to IEEFA. Some forecasts estimate that Cambodia's LNG-fired capacity could rise to as much as 2,700MW by 2040 and 8,700MW by 2050, stated the report. This would entail import requirements of 2.53mn t/yr in 2040 and 8.14mn t/yr in 2050. The fuel import costs for 2,700MW of LNG-fired capacity could amount to $1.08bn-2.17bn. LNG volatility LNG markets have been volatile over the past two years, because of factors such as geopolitical tensions and outages at supply facilities. Other emerging Asian economies such as Pakistan and Bangladesh faced fuel and power shortages because they have been unable to secure affordable LNG supplies, and this "demonstrates the evident risks of LNG importation for developing countries," states the report. Cambodia already has one of the highest electricity tariffs in Asia at $0.16/kWh, so higher LNG prices could require higher tariffs. LNG prices in Asia have been roughly $14/mn Btu and would have to fall below $5mn/mn Btu to compete with other electricity sources, according to IEEFA, but these low price levels are rare. The ANEA price, the Argus assessment for spot LNG deliveries to northeast Asia for the front-half month, stood at $15.08/mn Btu on 27 November. Cambodia's LNG demand and LNG-fired power plant expansions remain uncertain, so long-term offtake commitments will be challenging and the country will likely have to initially source cargoes from the sport market, according to the report. But the spot market poses risks in terms of supply security and price stability. Establishing an LNG supply chain also entails rigid long-term contracts that lock in fossil fuel infrastructure for decades. By Prethika Nair Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Uruguay's left-wing candidate wins presidency


25/11/24
News
25/11/24

Uruguay's left-wing candidate wins presidency

Montevideo, 25 November (Argus) — The left-wing opposition Frente Amplio will return to power in Uruguay after winning a hard-fought run-off election on 24 November. Yamandu Orsi, former mayor of the Canalones department, was elected president with close to 51pc of valid votes. He defeated Alvaro Delgado, of the ruling Partido Nacional. The Frente will control the senate, but will have a minority in the lower chamber. It last governed from 2015-2020. Orsi will take office on 1 March in one of Latin America's most stable economies, with the World Bank forecasting growth at 3.2pc for this year, much higher than the 1.9pc regional average. He will also inherit a country that has been making strides to implement a second energy transition geared toward continued decarbonization and new technologies, such as SAF and low-carbon hydrogen. He will also have to decide on future oil and natural gas exploration. Uruguay does not produce oil or gas, but has hopes that its offshore mimics that of Nambia, because of similar geology. TotalEnergies has made a major find there. The Frente's government plan states that it "will deepen the energy transition, focusing on the use of renewable energy, and decarbonization of the economy and transportation … gradually regulating so that public and cargo transportation can operate with hydrogen." On to hydrogen Uruguay is already the regional leader with renewable energy, with renewables covering 100pc of power demand on 24 November, according to the state-run power company, UTE. Wind accounted for 49pc, hydro 35pc, biomass 10pc and solar 6pc. Orsi will need to make decisions regarding high-profile projects for low-carbon hydrogen, as well as a push by the state-run Ancap to get private companies to ramp up oil and gas exploration on seven offshore blocks. The industry, energy and mining ministry lists four planned low-carbon hydrogen projects, including one between Chile's HIF and Ancap subsidiary Alur that would have a 1GW electrolyzer. Germany's Enertrag is working on an e-methanol project with a 150MW electrolyzer, while two Uruguayan groups are working on small projects with 2MW and 5MW electrolyzers, respectively. The Orsi government will also need to decide if it continues with Ancap's planned bidding process for four offshore blocks, each between 600-800km² (232-309 mi²), to generate up to 3.2GW of wind power to produce 200,000 t/yr of green hydrogen on floating platforms. The Frente has been noncommittal about the future of seven offshore oil and gas blocks, including three held by Shell, two by the UK's Challenger — which recently farmed in Chevron — and one each by Argentina's state-owned YPF and US-based APA Corporation. The Frente's government plan states that "a national dialogue will be called to analyze the impacts and alternatives to exploration and extraction of fossil fuels." By Lucien Chauvin Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Generic Hero Banner

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more