Latest market news

Few 2024-25 LNG cargoes scheduled at Alexandroupolis

  • Market: Natural gas
  • 17/10/24

Users of Greece's new Alexandroupolis LNG terminal have so far only scheduled seven LNG deliveries for the 2024-25 gas year, according to a schedule sent to Argus by terminal operator Gastrade.

TotalEnergies delivered the year's first 1TWh cargo to Bulgargaz on 3 October and the French company is scheduled to bring further 1TWh shipments to Bulgargaz on 25 November and 27 December. And next year, only one cargo is scheduled to arrive each month in January-March — the March shipment being only 509GWh — before a four-month gap until a final scheduled delivery of 509GWh on 27 July (see data and download).

Although still subject to change if spot slots are purchased or swapped in the future, those 6TWh of scheduled deliveries would utilise only a fraction of the terminal's full 66.3 TWh/yr capacity.

Such low utilisation is despite the fact that 69pc of the terminal's capacity is booked for the current gas year, according to the operator. With prices on Bulgaria's Balkan Gas Hub frequently at least €5/MWh ($5.4/MWh) below the TTF, firms have little incentive to bring LNG to Greece. Imports to Greece's Revithoussa terminal have more than halved so far this year, despite much higher Greek consumption.

And the full 90pc of Alexandroupolis' capacity is booked for the 2025-26 and 2026-27 gas years, with just the EU-mandated 10pc held back for offer as prompt products. Bookings drop slightly in the following three years before falling more significantly from 2030 onwards (see bookings table).

The Alexandroupolis terminal is currently undergoing scheduled maintenance on the 15-18 October gas days, halting sendout. Works are also scheduled to freeze sendout on 7-14 June 2025.

There are currently 14 registered users at Alexandroupolis. As well as some of the main regional players such as Bulgargaz, OMV Petrom, Edison, and Depa, there are also some smaller companies such as Attiki Gas Supply, Tibiel EOOD, and Sustainable Energy Supply (see supplier table).

Alexandroupolis registered users
ATTIKI GAS SUPPLY COMPANY S.A.
BULGARGAZ EAD
DEPA COMMERCIAL S.A.
EDISON SpA
HERON ENERGY S.A.
OMV PETROM S.A.
PUBLIC POWER CORPORATION OF GREECE S.A.
PREMIER ENERGY SRL
SK GAS MED
PUBLIC COMPANY SRBIJAGAS NOVI SAD
JSC Power Plants of North Macedonia - AD Elektrani na Severna Makedonija (AD ESM - Skopje)
TIBIEL EOOD
SUSTAINABLE ENERGY SUPPLY LTD
VENTURE GLOBAL LNG
Alexandroupolis capacity bookingsGWh/d
Gas yearTechnical capReserved capAvailable capAvailable short-term cap
2025-2026181.6163.40.018.2
2026-2027181.6163.40.018.2
2027-2028181.6158.45.018.2
2028-2029181.6158.45.018.2
2029-2030181.6138.624.818.2
2030-2031181.699.364.218.2
2031-2032181.694.369.218.2
2032-2033181.694.369.218.2
2033-2034181.694.369.218.2
2034-2035181.631.4132.118.2
2035-2036181.631.4132.118.2
2036-2037181.631.4132.118.2
2037-2038181.631.4132.118.2
2038-2039181.631.4132.118.2

Sharelinkedin-sharetwitter-sharefacebook-shareemail-share

Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

News
17/10/24

Pemex to cut 20pc of upstream budget in 4Q

Pemex to cut 20pc of upstream budget in 4Q

Mexico City, 17 October (Argus) — Mexico's state-owned Pemex plans to reduce its upstream budget by 20pc in the fourth quarter, impacting short-term crude production, according to industry sources and internal documents. Pemex's new upstream head, Nestor Martinez, has instructed the company's units to implement budget cuts in activities such as major well repairs and seismic data contracts, according to documents seen by Argus . The company aims to save Ps26.78bn ($1.38bn) in 2024, according to an internal presentation of Pemex's upstream arm (PEP) dated 9 October. Pemex typically spends around Ps130bn quarterly, so the cut represents about 20pc of that, said an industry source. Pemex did not respond a request for comment. The reduction could lower Pemex's crude production by 5,804 b/d, according to the document. But the actual impact may be greater if wells go without essential repairs and stop production, sources added. Pemex produced 1.73mn b/d of crude and condensates in August, according to hydrocarbon regulator CNH data. This budget cut signals ongoing issues with delayed payments to Pemex vendors, which has worsened over the past six years, according to market sources. The cuts also suggest that President Claudia Sheinbaum's target of maintaining oil output below 1.8mn b/d could lead to further reductions in exploration and production spending. As of 2 October, PEP owed around Ps99bn to suppliers, with Ps81bn for 2024 work, Ps10.5bn from 2023, and Ps1.9bn from 2022, according to an internal document sent by PEP to its units on 11 October. In July, Pemex reported Ps126.4bn in overdue payments across all units. Oil services companies GMS Bronco, Typhoon Offshore, Cotemar, Perforadora Integral de Orienta and Baker Hughes had the five highest outstanding balances as of 2 October, according to the internal document. Dowell Schlumberger and Halliburton de Mexico, subsidiaries of SLB and Halliburton, were among the10 companies owed the most by Pemex. By Édgar Sígler Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Find out more
News

Australia’s Santos commissions Moomba CCS facility


17/10/24
News
17/10/24

Australia’s Santos commissions Moomba CCS facility

Adelaide, 17 October (Argus) — Australian independent Santos has commissioned its 1.7mn t/yr Moomba carbon capture and storage (CCS) project in the onshore Cooper basin of South Australia state, the firm said in its July-September results. The Australian carbon credit unit (ACCU)-generating project is running at full injection rates of up to 84mn ft³/d (2.38mn m³/d) of CO2 with all five wells on line, Santos said, adding that the full 1.7mn t/yr capacity would depend on Cooper basin gas production. The CCS will be Australia's second largest by nameplate capacity after Chevron's controversial 4mn t/yr Gorgon CCS on Barrow Island, which has been criticised for failing to reach its sequestration goals because of issues with the pressure management system. Santos reported July-September output 3pc down from 22.2mn bl of oil equivalent (boe) in the previous quarter to 21.6mn boe. This was primarily because of planned maintenance at amine trains at its Varanus Island plant and natural field decline in Western Australia state. Condensate production fell by 97pc from 329,100 bl to 9,000 bl for the quarter because of field decline and shutdown at the Ningaloo Vision floating production, storage and offloading vessel (FPSO) because of a subsea communications fault, expected to return to service in early to mid October-December quarter. Santos completed decommissioning of 13 wells within the Harriet joint venture and three of 11 wells in the Mutineer, Exeter, Fletcher and Finucane fields. The 7.8mn t/yr Gladstone LNG shipped 21 cargoes for the quarter, one less than a year and quarter earlier. LNG production was similar to the previous quarter because of seasonal shaping to meet domestic winter gas requirements. Growth is expected in October-December owing to new wells from Arcadia and Roma fields. Angore field in Papua New Guinea is being commissioned and will start production of about 350mn ft³/d in October-December, Santos said, in line with previous guidance. The Barossa backfill project offshore northern Australia is 82pc complete with FPSO integration continuing in Singapore and three of six wells completed. Santos' Pikka phase one project is 67pc complete, with Alaskan authorities approving a 25pc increase in the acreage in September. But the project's costs would increase by about 20pc, or around $520mn from the original $2.6bn estimate, because of inflation and accelerated pipelay activity costs, Santos said. This would take the cost of Pikka, which was sanctioned in mid-2022 to $3.12bn. Santos controls 51pc and Spanish energy firm Repsol owns 49pc of the asset. Santos expects its 2024 production to be at the upper end of its guidance of 84mn-90mn boe. By Tom Major Santos results Jul-Sep '24 Apr-Jun '24 Jul-Sep '23 y-o-y % ± q-o-q % ± Volumes ('000 t) GLNG (100pc) 1,300 1,338 1,370 -5 -3 Darwin LNG (100pc) 0 0 42 -100 -100 PNG LNG (100pc) 1,938 2,001 2,111 -8 -3 Santos' equity share of LNG sales 1,148 1,264 1,300 -12 -9 Financial LNG sales revenue ($mn) 766 762 821 -7 1 Total sales revenue ($mn) 1,269 1,313 1,436 -12 -3 LNG average realised price ($/mn Btu) 12.69 11.47 12.02 6 11 Oil price ($/bl) 83.24 89.48 89.97 -7 -7 Source: Santos Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

'No reason' for Cyprus gas monopoly: Cyfield


16/10/24
News
16/10/24

'No reason' for Cyprus gas monopoly: Cyfield

London, 16 October (Argus) — There is "no reason" for the gas market monopoly given to state-owned Cygas to continue given sufficient private-sector interest in investing, the chief executive of construction and energy conglomerate Cyfield, George Chrysochos, has told Argus . Cyprus gave Cygas the monopoly thinking that it was the only feasible way to cover the large cost of developing the Vasilikos LNG import terminal, but the government has since been "extremely slow and inefficient in completing the terminal", Chrysochos said. And since 2019, private investors — notably regional producer Energean — have shown increasing interest in Cyprus' gas market, "indicating that there is no reason for the monopoly to exist", he said, adding that a competitive liberalised market would reduce the price of gas imports and therefore also domestic electricity production. The Vasilikos project is currently under investigation by national and European authorities on suspicion of procurement fraud, misappropriation of EU funds and corruption. The project's shared liability between disparate companies made it "impossible for many parties to show interest", Chrysochos said. Completing the project is a priority for Cyprus and that can be done in one of two ways, he said. Either state-owned developer ETYFA could issue a new construction tender using EU and Cypriot funds, which could potentially be completed within a year, or ETYFA could "give the terminal as a concession" to a new operator that finances all remaining work, operates the facility and pays annual rights to Cygas, Chrysochos said. The "ideal scenario" for bringing gas to Cyprus would be to build a pipeline directly to existing Israeli offshore fields, and if funding for a pipeline to Israel's Karish field were available, that would "definitely bring cheaper gas to Cyprus", he said. "All redundancies are welcome," he added. But with Vasilikos already 80pc complete and its floating storage and regasification unit (FSRU) purchased, completing the terminal is the "most reasonable option", Chrysochos said. Cyprus has made several large gas discoveries in its exclusive economic zone, but has been unable to develop them commercially. "Cyprus is a small market and cannot serve as a starting point that will make this extraction feasible," Chrysochos said, meaning that "the viability of the project depends 100pc on the sale of these quantities abroad." Because of this, the only "feasible way" for Cyprus to utilise its discoveries is to pipe the gas to Egypt, where it can be liquefied and then exported back to Cyprus or elsewhere, he said. Alternatively, a pipe could be built to bring gas directly to Cyprus from the Aphrodite field. The consortium developing Aphrodite submitted plans to pipe processed gas to Egypt in September , with similar plans for production at Cronos . Cyfield subsidiary Power Energy Cyprus has been building a 260MW combined-cycle gas turbine (CCGT) plant, which had been intended to be fully operational by early 2025. The construction works are almost complete, but if delays to the Vasilikos terminal prove "significant", the firm might opt to modify the plant to run on diesel, which would require "significant" capital expenditure, Chrysochos said. In any case, Cyfield supports the government in completing Vasilikos and hopes that the CCGT will be operational with either gas or diesel in the next 12 months, he said. Considering the small size of the Cypriot market and that the Electricity Authority of Cyprus is building another power plant, Cyfield now plans to gradually shift its focus for the future to storage and renewables, he said. The proposed 1GW Great Sea electricity interconnector with Greece, approved by the Cypriot council of ministers last month , poses a "greater threat" to local generation than it offers in terms of opportunities, Chrysochos said. Because the scale of energy projects in Greece and Europe is much larger than in Cyprus, the levelised cost of energy is lower, so "it is almost impossible at this stage for Cyprus to export electricity to Europe", he said. The Great Sea line would probably make Cypriot generation redundant and would also be "extremely expensive for the Cypriot consumer, which means that any benefit from importing electricity from Greece will never outweigh the cost", he said. By Brendan A'Hearn Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Ecuador authorizes LNG import terminal


15/10/24
News
15/10/24

Ecuador authorizes LNG import terminal

Quito, 15 October (Argus) — Ecuador's hydrocarbons regulator (Arch) authorized the domestic firm Pacific Terminal to build a maritime terminal in Monteverde, Guayas province, to import and store LNG. The project includes an LNG unloading pier, a 630m (2,066 ft) long access ramp, mooring dolphins and a maneuvering platform. According to Pacific Terminal's website, the project includes regasification systems and a 100km-long (62mi) gas pipeline to connect the Monteverde plant with the city of Guayaquil, Ecuador's main port. The company plans to supply natural gas mainly to the region's shrimp farming industry, but also to plastic, cement, glass and other plants. Pacific Terminal also aims to provide natural gas to thermoelectric plants. According to the firm, replacing diesel and fuel with natural gas would save privately owned industries in the country around $500mn/year. Pacific Terminal did not immediately reply to a request for more details. Arch gave Pacific Terminal a deadline of five years to build the terminal and complete the project. Pacific Terminal is the second company to be authorized to import LNG in Ecuador. The first company to be authorized was Miami-based Sycar which started importing LNG in 2022, but halted it in May of that year. Currently, the only natural gas consumed in Ecuador is that produced by the Amistad field operated by Petroecuador. Its production averaged 20.6mn cf/d from January-August, down by 3pc compared with the same period of 2023, according to data from the state-owned company. By Alberto Araujo Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Lignite displaces gas in German power mix


15/10/24
News
15/10/24

Lignite displaces gas in German power mix

London, 15 October (Argus) — Rallying German gas prices have pushed a significant amount of gas-fired generation out of the country's power mix this month, opening space for lignite. Average daily gas-fired generation in Germany has slipped to 3.8GW so far this month from 4.2GW in September and August and 4.1GW in July. During that time, lignite-fired generation climbed to 9GW from 7.2GW in September and August and 7.4GW in July. Coal-fired generation has also edged down to 2.9GW so far this month from just over 3GW in September, but higher than the averages of 2.3GW in August and 1.4GW in July. Meanwhile, supporting demand for thermal-fired generation, German renewables output has fallen to 30.3GW so far in October from just under 32GW in September when wind generation stepped up, but slightly above the 29.5GW in August when wind output was lower. Remaining German power demand in recent weeks has been covered by imports, which have risen to a net 3.8GW so far this month from 3.4GW in September, but remained well below the 6.2GW in August. Electricity imports from neighbouring countries such as France are occasionally cheaper than domestic generation and can help fill in gaps between German power demand and supply. A combination of changing renewable output, higher gas prices, stable lignite prices and lower emissions prices have spurred changes in the German power mix. The German THE day-ahead has risen strongly since late July and prices have rallied in recent weeks against a backdrop of rising geopolitical tensions in the Middle East. Meanwhile, German lignite-fired plants typically source fuel from nearby mines, substantially insulating domestic lignite prices from external market forces. German regulator Bnetza assumed earlier this year that domestic lignite would cost about €3/MWh in 2024-25. At the same time, near-term prices in the EU emissions trading system (ETS) — a key driver of competitiveness for German lignite-fired generation — have fallen. Prompt ETS allowances closed at €65.36/t of CO2 equivalent (CO2e) on Monday, down from €72.14/t CO2e on 19 August, boosting the profitability of lignite-fired plants, which are the more CO2 intensive than coal and gas. Those recent price shifts have made output from lignite-fired plants with a typical efficiency of 36pc more profitable than normal 55pc-efficient gas-fired plants as well as coal-fired stations operating at 40pc efficiency, which have also become more profitable . By contrast, in the first eight months of this year, 36pc-efficient lignite-fired plants had competed tightly with 55pc-efficient gas-fired plants even as gas prices fell to the bottom of the coal-to-gas fuel-switching range ( see fuel-switching graph ). Buffer zone More competitive lignite-fired generation has also started acting as the domestic buffer to cover gaps between supply and demand left by renewable generation ( see power generation graph ). After Germany renewable generation dropped to 26.8GW on 2-9 October from a strong 45.5GW on 26-28 September, lignite-fired generation jumped to 10.1GW from 6.4GW — a 57pc gain — while gas-fired output only rose to 3.5GW from roughly 3GW and coal-fired generation increased to 2.9GW from 2.3GW. In December-July, when the gas and lignite fuel-switching range was tight, generation from both fuels reacted similarly to fluctuations in renewable output and both plant types buffered their generation based on demand ( see power generation graph ). And forward prices assessed by Argus suggest that lignite-fired generation could remain competitive against gas and coal-fired output in the German power mix next month. As of market close on Monday, November-dated fuel and emissions prices would place the operating costs of a 36pc-efficient lignite-fired plant during that time below those of a 55pc-efficient gas-fired plant and a 40pc-efficient coal-fired plant. That said, Germany's decreasing lignite and coal-fired generation capacity limits how much of the national power mix those plant types can provide. As of April, Germany had 82.4GW of gas-fired capacity, but just 15.1GW of lignite-fired capacity and 11.5GW of coal-fired plants, according to Bnetza. By Lucas Waelbroeck Boix Fuel switching range €/MWh Power generation by fuel, 7 day average GW Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Generic Hero Banner

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more