Latest market news

Q&A: Cyprus eyeing first gas production in 2027

  • Market: Natural gas
  • 13/11/24

Cyprus has made five considerable offshore gas discoveries since 2011. But more than a decade on, none has been developed. Argus sat down with Cyprus' energy minister, Giorgos Papanastasiou, at the Adipec conference in Abu Dhabi last week to discuss how things are progressing at a number of these projects, and how current regional tensions are affecting plans. Edited highlights follow:

How are the five discoveries in Cyprus' exclusive economic zone (EEZ) progressing? Could we start with the 2.5 trillion ft³ Cronos discovery in block 6?

At this point, we are expecting the development and production plan (DPP) from [operator Italian firm] Eni, which it promised will be delivered at some time in November-December. We expect it will have two phases. The fast-track, which is phase 1, and phase 2, which will recover more gas from the well. The direction is via the infrastructure of the Zohr field [in Egypt].

Has it actually been decided that the gas from Cronos will be recovered through Zohr infrastructure? We understand that there was a disagreement with TotalEnergies, Eni's partner, on this.

It is being discussed. But you ultimately need to see it in the DPP. Unless you have the DPP signed off by the government of Cyprus, you won't have an agreement. But up until this point in time, there have been verbal conversations.

To be clear then, there is no disagreement between TotalEnergies and Eni at the moment?

No — it is not there. That is the plan of Eni which verbally has been accepted [by the Cypriot government].

What is TotalEnergies' stance? Do they also have to be on board?

This is something between the partners. But as far as we are concerned, this [tie-back to Zohr] is acceptable. If this is what they will deliver in the DPP, that would be fine with us. It will be a tie-back to the Zohr facilities, and connected to Egypt's 5.5mn t/yr Damietta LNG export terminal.

And this is Cyprus' preference?

The preference was to have a floating production unit [FPU] to achieve higher recoverability. But we still understand that the fast-track as well, which means that first gas without the FPU, will be in 2027. So that is important for us as well.

So discussions between the two companies, as far as you are concerned, are for them to sort out?

They will sort it out. However we communicated to Eni that at every stage of any agreements they have with any party, we have to be part of it and do a sense check.

As for the timeframe for such an agreement — is it correct that their licence for block 6 is set to expire next year? Is time on their side?

Not for Cronos, no. But in any case, if it is expiring for Cronos, we will extend it. Of course.

Given the current state of discussions, when do you expect production to start at Cronos?

Eni's target is to get the first gas to the surface in the first six months of 2027.

And how about Aphrodite — Cyprus' first ever discovery in 2011 — how are things progressing there?

On Aphrodite, we have given an extension to the operator until the middle of January. They have provided a revised initial plan which is not completed yet, but it is heading in the right direction. And the right direction for us is what was agreed in the past, in 2019, which includes an FPU, a short pipeline to Egypt for domestic [consumption] or liquefaction.

As far as Cyprus is concerned, you are happy with the latest plan on the table?

I believe this time we are happy, yes. And not only that, but we also see some traction on behalf of the operator as well.

Are you expecting production at Aphrodite to also potentially begin in 2027?

Aphrodite, I don't think it will be 2027. In the current circumstances it very much depends on what we see as the final DPP. Also on when the pre-Feed [front-end engineering and design] will be done, the Feed and the FID [final investment decision]. But the way it's progressing, it could be 2030.

So the 2022 Cronos discovery would be the first to come on stream?

Yes, because of the existence of infrastructure that is only a few kilometres away.

And how about the 5 trillion-8 trillion ft³ Glafcos discovery from 2019?

At Glafcos, the operator is ExxonMobil. It will be doing more drilling in the area of block 10 and block 5, and depending on any new discoveries, it will decide how to commercialise it.

So, as of now, with the discoveries that have been made to date, is that not considered for commercialisation?

This is a difficult question — it's for the operator to decide. But we believe that Glafcos on its own is a discovery that can be commercialised. Smaller discoveries and quantities by far in the world have been developed. But it depends on the appetite of the operator.

Assuming first production in 2027, what is the plan for this gas?

There won't be any connection directly to Cyprus. But indirectly there will be a connection, and when there is some gas, that will be liquefied and find its way back to Cyprus. As soon as we have the facilities — the FSRU [floating storage and regasification unit] and the facilities operating, which will happen sometime at the end of 2025, or the beginning of 2026 — we can get some product in kind, liquefy it and get it back for regasification. The FSRU is already constructed. We are receiving it sometime in the next few days, hopefully. There was an agreement between the contractor and the public company of natural gas, and it will be sailing from Shanghai in the next few days.

With heightened tensions in the region, have you seen any impact on companies' appetite or activities offshore Cyprus?

To be honest, in energy we haven't seen any reluctance because of the turmoil. Other investments onshore, there are some assessments that the investors are doing. But when it comes to energy… you know that you can use energy to bring some stability. And we want to believe that through Cyprus' EEZ and wealth that sits there, Cyprus can be a contributor through energy to create some stability. This is exactly what is happening with Egypt. Egypt needs product for its domestic market. The more the product, the more the stability, because you provide electricity, which is a commodity for the citizens of Egypt. At the same time, through the Damietta or Idku LNG terminals, we can get some product for the international markets which can be converted to income for the citizens of Cyprus.

And with regard to security and infrastructure in the east Mediterranean?

No, no — we haven't seen anything, but there is some vigilance. Cyprus has a good relationship with all the world. We are not taking any sides, supporting any party, and try to be very careful about how we behave in the neighbourhood there.


Sharelinkedin-sharetwitter-sharefacebook-shareemail-share

Related news posts

Argus illuminates the markets by putting a lens on the areas that matter most to you. The market news and commentary we publish reveals vital insights that enable you to make stronger, well-informed decisions. Explore a selection of news stories related to this one.

News
16/12/24

Qatar Energy wins Gail LNG supply deal for five years

Qatar Energy wins Gail LNG supply deal for five years

Mumbai, 16 December (Argus) — QatarEnergy has won a bid to supply 12 cargoes a year to Indian state-run gas distributor Gail under a five-year LNG supply contract beginning in 2025, according to market sources. Gail floated a tender in early November , inviting bids for supplies of LNG from April 2025 until March 2030, with prices linked to the US Henry Hub (HH) on a delivered basis to India's west coast, according to a tender document seen by Argus . The tender closed on 13 December. QatarEnergy will supply LNG at 115pc HH in addition to a constant of $5.6/mn Btu, sources told Argus . Gail in turn has contracted with downstream customers in India at a contract price of 119pc HH in addition to a constant of $6/mn Btu, according to documents seen by Argus . "Typically, a Henry hub linked contract only makes sense when it is for 10-15 years. But this tender is a unique one as it is just for five years," a source told Argus . What is unclear is the source of supply. QatarEnergy and ExxonMobil's 15.6mn t/yr Golden Pass LNG project has been delayed after lead construction contractor Zachry Holdings filed for bankruptcy in March, according to a Federal Energy Regulatory Commission filing, prompting US federal regulators to give a three-year extension to finish building the plant. The agreement with Gail may equate 3.6mn t of LNG supply over the five-year period to 2030, assuming a 60,000t LNG cargo size, and add to Gail's existing 5.8mn t/yr of LNG supply under a 20-year agreement from US' Sabine Pass and Cove Point on a fob basis till 2038. The deal is also likely to support the demand for India's city gas distribution network as the government abruptly cut domestic gas allocations to city gas distribution firms in the past two months. Gail aims to add 5mn-6mn t/yr of medium-to-long-term LNG contracts to take its overall LNG portfolio to 20mn-21mn t/yr by 2030 in addition to its existing long-term LNG portfolio of 15.38mn t/yr. By Rituparna Ghosh Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Find out more
News

US’ Plaquemines LNG terminal achieves first production


16/12/24
News
16/12/24

US’ Plaquemines LNG terminal achieves first production

Singapore, 16 December (Argus) — US-based LNG developer Venture Global has achieved first production at its planned 27.2mn t/yr Plaquemines LNG terminal, the firm announced on 14 December. The terminal is still undergoing commissioning, but it will start producing and exporting LNG, the firm said. Venture Global is targeting full commercial operations at the terminal in mid-2027, according to a filing with the US Department of Energy (DOE) in October. The terminal's first phase, with a 13.3mn t/yr base-load capacity, is set to start commercial operations in mid-2026, and the second phase, with a base-load capacity of 6.7mn t/yr, in mid-2027. The 36 trains will have a peak capacity of 27.2mn t/yr. Venture Global had planned a 24-month commissioning phase for Plaquemines. But the early operation is possible because of the project's unique configuration and construction approach, which enables production even as construction and commissioning works for the remainder of the project's 36 trains continue, the firm added. The ability to produce and export LNG during the commissioning phase enables the company to accelerate the supply of additional LNG to the global market, outpacing other suppliers, the firm said. This incremental supply has proven to be a critical asset given historically tight global LNG markets and project delays, it added. Venture Global also sold commissioning cargoes to the spot market until commercial operations are reached at its 12.4mn t/yr Calcasieu Pass terminal. US energy regulator Ferc in late November approved the first phase of the Gator Express pipeline to enter service, after the second phase was approved for service in April. The pipeline will supply feedgas to Louisiana's planned 27.2mn t/yr Plaquemines LNG export terminal. The Plaquemines LNG export facility is Louisiana's fourth liquefaction terminal. By Joey Chan Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

BP and Adnoc form Egypt-focused gas joint venture


16/12/24
News
16/12/24

BP and Adnoc form Egypt-focused gas joint venture

Dubai, 16 December (Argus) — BP and Abu Dhabi's state-owned Adnoc have set up a natural gas joint venture which will initially focus on developing assets in Egypt, the companies said today. BP will hold a 51pc stake in the venture, named Arcius Energy, while Adnoc's recently formed energy investment unit, XRG, will have the remaining 49pc. Arcius Energy "will combine the pair's deep technical capabilities and proven development track record as it aims to grow a highly competitive gas portfolio", Adnoc and BP said in a joint statement. Today's announcement comes around 10 months after the companies first revealed their intentions to form the joint venture in the second half of 2024. At the time, they said it would focus on Egypt, but they suggested today that Arcius Energy's scope could extend elsewhere. "Arcius Energy, initially to operate in Egypt, includes interests assigned by BP across two development concessions, as well as exploration agreements," the firms said. The assets assigned to Arcius Energy include BP's 10pc stake in the Shorouk concession, which contains the giant Zohr gas field, and the North Damietta offshore block in the Nile Delta. Also included are BP's exploration agreements covering the North El Tabya, Bellatrix-Seti East and North El Fayrouz concessions. In February, the firms said BP would transfer to the new venture a 50pc interest in the North El Burg offshore concession, where four gas discoveries have been made since 2008. But there was no mention of this in today's announcement, implying a change of plan. Naser Saif al-Yafei has been appoimnted the new venture's chief executive. He has worked for Adnoc for close to 20 years, most recently as senior vice-president for strategy, sustainability and transformation. Katerina Papalexandri will be chief financial officer. She has been at BP for more than 20 years, most recently as vice-president gas and low-carbon energy growth for the Caspian region. By Nader Itayim Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

Canada sets 2035 emissions reduction goal


13/12/24
News
13/12/24

Canada sets 2035 emissions reduction goal

London, 13 December (Argus) — Canada has set a new 2035 climate goal, aiming to reduce its greenhouse gas emissions by 45-50pc by 2035, from a 2005 baseline. This builds on its 2030 target of a 40-45pc emissions reduction, again from 2005 levels. Canada's emissions had been in 2015 projected to rise by 9pc by 2030, from 2005 levels, "but we are now successfully bending the curve", the Canadian environment and climate change ministry said. The newly-announced target is in line with a pledge Canada made at the UN Cop 29 climate summit last month. Countries that are party to the Paris climate accord must submit new national climate plans by 10 February 2025, to cover a timeframe up to 2035. Canada, the EU, Mexico, Norway and Switzerland committed at Cop 29 to set out new plans with "steep emissions cuts" that are consistent with the global 1.5°C temperature increase limit sought by the Paris Agreement. The plans are known as nationally determined contributions (NDCs). Canada's NDC is being considered by the cabinet, and the country plans to submit it by the deadline, Canadian climate change ambassador Catherine Stewart told Cop 29 delegates on 21 November. Tackling climate change is "both an environmental imperative and an economic opportunity", she added. The target was informed "by the best available science, Indigenous Knowledge, international climate change commitments, consultations with provinces and territories and expert advice", the ministry said. Canada will also "seek feedback on how to help companies take advantage of the economic opportunities that come with building a clean economy" in the near term, it added. Although the plan is not yet available, the ministry said that it will examine the role of carbon removal technologies for the energy transition. "Canadians are increasingly experiencing record-breaking extreme weather," the ministry noted. The country experienced record wildfires in 2023. Carbon emissions from wildfires this year were second only to the "unprecedented" levels in 2023, EU earth-monitoring service Copernicus found this month. Canada has a legally binding target of net zero emissions by 2050. By Georgia Gratton Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

News

India's Gujarat Gas raises PNG prices in Morbi cluster


13/12/24
News
13/12/24

India's Gujarat Gas raises PNG prices in Morbi cluster

Mumbai, 13 December (Argus) — India's state-run city gas distribution company Gujarat Gas has increased prices of piped natural gas (PNG) in the Morbi industrial cluster in west India's Gujarat state. This came after it kept rates unchanged since July. Prices of PNG used in the industrial ceramic cluster have been hiked to 46.95 rupees/m³ ($0.55/m³) from Rs44.68/m³ in July. This comes to Rs5.60/kcal on an energy equivalent basis, based on a calorific value of 8,400 kcal/kg. This is slightly higher than propane prices, which is a competing fuel in the region's ceramic cluster. Propane prices in Morbi were pegged at Rs61/kg for December , up from Rs60.30/kg in November because of rising import costs. Propane on an energy equivalent basis is Rs5.50/kcal based on the calorific value of 11,100 kcal/kg, traders said. Gujarat Gas has regained some market share in the last few months by keeping its prices unchanged. But it remains to be seen if ceramic units in the region will switch back to propane again. Propane demand in the region fell to 3.2mn m³/d in November from 4.5mn m³/d in October, regional traders said. Overall gas demand in the region was 7mn m³/d in November. Capacity utilisation of ceramic clusters continues to remain weak because of lower export demand for the upcoming Christmas season in the west, according to traders in the region. Gujarat Gas competes with regional propane distributors, including state-controlled IOC, BPCL and HPCL, as well as private-sector firms Reliance Industries, Aegis Logistics and Gogas. It remains to be seen if propane prices will rise further next month, as Saudi Arabia's state-controlled Aramco kept its December propane contract price unchanged at $635/t. Spot LNG prices have also risen this month, which makes a fall in PNG prices unlikely. The Argus -assessed spot price of LNG delivered to India's west coast for first-half January stood at $14.09/mn Btu on 12 December, up from $12.70/mn Btu a month earlier for December-arriving vessels. Tile manufacturers in Morbi have been switching between PNG and propane depending on LNG import prices, since the latter rose in 2022 as a result of the Russia-Ukraine war. By Rituparna Ghosh Propane vs PNG prices (Indian rupees/kcal) Send comments and request more information at feedback@argusmedia.com Copyright © 2024. Argus Media group . All rights reserved.

Generic Hero Banner

Business intelligence reports

Get concise, trustworthy and unbiased analysis of the latest trends and developments in oil and energy markets. These reports are specially created for decision makers who don’t have time to track markets day-by-day, minute-by-minute.

Learn more